  • Street level view of Lincoln Way at Kezar Drive

Contract No. 65 New Traffic Signals

San Francisco Public Works has partnered with SFMTA to improve safety at several intersections throughout the city. Contract No. 65 New Traffic Signals will add new traffic signals at 7 key intersections

Every year in San Francisco, about 30 people lose their lives and over 500 are severely injured while traveling on city streets. These deaths and injuries are unacceptable and preventable. In 2014, the City and County of San Francisco adopted Vision Zero as a policy, with the goal of building better and safer streets in San Francisco. These improvements will increase safety for pedestrians, bicyclists and motorists.

The scope of work will include excavation at the intersections, new traffic pole installation and electrical conduit work. Some intersections will also include curb ramp installation. 

The intersections scheduled for improvements are listed below:

  • 9th Street - San Bruno & Division - Under construction
  • Kezar Drive and Lincoln Way - Under construction
  • Hattie Street and Market Street - Under construction / scheduled to be complete in February 2024
  • Loomis Street and Oakdale Avenue - Under construction 
  • Alemany Boulevard and Rousseau Street - Under construction / scheduled to be complete in early 2024
  • Alemany Boulevard and Theresa Street - Under construction / scheduled to be complete in early 2024
  • Alemany Boulevard and Lawrence Avenue - Under construction / scheduled to be complete in early 2024
Transportation Projects
Public Safety
STATUS In Progress
Location
Throughout San Francisco
Start Date November 14, 2022
Completion Date November 30, 2023
Release Date
Wednesday, October 12, 2022
Budget
$3.8 Million
Project Manager
Edmund Lee
Project Team

San Francisco Public Works

SFMTA

Liffey Electric, Inc.

(415) 400-5182 (Office)

(415) 871-1463 (After Hours/Urgent)

Contact
Alex Murillo
Phone
(628) 271-2244