Main menu

  • VL55 18th Street

Various Locations Pavement Renovation and Sewer Replacement No. 55

Project Update (April - May 2024)

Bryant St (21st St to 26th St)
4-April  to 12-April                Miscellaneous Concrete Parking Strip & Concrete Flatwork      
15-April to 19th-April            Roadway Paving (each block will be 2-days duration)
 
21st St (Florida St to Harrison St)
8-April to 3-May                    Sewer-main and manhole replacement including lateral lines as-needed. Installation of AWSS (emergency water supply) monitoring points
 
Harrison St (24th St to 25th St)
18-April to 17th-May             Sewer-main and manhole replacement including lateral lines as-needed. Installation of AWSS (emergency water supply) monitoring points           

 

Project Description
San Francisco Public Works has contracted with our contractor, D'Arcy and Harty to install new sewer utilities and renovate the roadway at various locations in San Francisco as part of the Various Locations Pavement Renovation and Sewer Replacement No. 55 (VL55)  

  • Linda Street (19th St to End) - COMPLETED
  • 18th Street  (Dolores St to Valencia St) - COMPLETED
  • 21st Street (Florida St to Harrison St)
  • 22nd Street (South Van Ness Ave to Mission St)
  • 22nd Street (Guerrero St to Chattanooga St)
  • 23rd Street (Guerrero St to Chattanooga St)
  • 25th Street (York St to Florida St)
  • 25th Street (Lucky St to Shotwell St)
  • 25th Street (South Van Ness Ave to Capp St)
  • Harrison Street (24th St to 25th St)
  • Bryant Street (26th St to Cesar Chavez St)
  • Bryant Street (21st St to 25th St)
  • Cesar Chavez Street (Guerrero St to Church St)
  • Cesar Chavez Street (Sanchez St to Noe St)
     

Work will consist of pavement renovation (including base-repair and bus-pad replacement), curb ramp construction, sewer replacement, traffic control, and all related work. Sewer work will involve some street excavation to install new utilities and will be followed by pavement renovation (i.e. grinding and paving) activity once all utility work is complete. No interruption of sewer service is expected during construction. There may be a delay between utility work and final roadway renovation activity.

The typical sequence of sewer work is to install the new sewer main along the block(s) followed by sewer lateral replacement. Once the sewer main has been installed, Public Works’ engineering team will review video of the sewer laterals to determine which, if any, need to be replaced. The sewer laterals are the connection between the main and the sidewalk/curb. Crews will then schedule the sewer lateral replacement work. Sewer laterals are replaced on an as-needed basis depending on the condition of the line. Sewer service will not be interrupted during construction. Please continue to use your household plumbing as usual. 

During construction, traffic control will be implemented and "No Parking/Tow Away Zone" signs will be posted in active work areas. Local access for residents, deliveries and emergency services will be provided at all times during work hours. Please limit your use of the roadways within the construction work areas during working hours for the safety of the public and our employees, and to park in driveways or on adjacent blocks when No Parking Zones are posted. Should you need access to your property during work hours, please alert a crew member on site and note that there may be a slight delay to enter or exit your property to allow for crews to create a safe path of travel. Please follow instructions from crew members and follow all posted detour signs.

(*Please note:  Construction schedules, dates and durations are estimates subject to change due to rain, equipment breakdown, unforeseen field conditions, existing utility conflicts, crew availability, or early/delayed completion of work at a prior location.)

Pavement and Sewer Renovation
Start Winter, 2023
Completion Summer, 2024
Release Date
Thursday, September 1, 2022
Project Team

Contractor Contact: Darcy and Hardy

Michael D'Arcy, Project Manager

415-822-5200 after hours emergency Contact : Gaelen O'Toole 415-559-3325 (cell)

 

Contact
Dadisi Najib, Public Affairs
Phone
628-271-2245