Eureka, Grand View and Mangels Pavement Renovation, Sewer Replacement and Water Main Installation Project

This project will involve the renovation and improvement of Eureka Street between 23rd Street and Market Street, Grand View Avenue between Clipper Street and Market Street, Mangels Avenue from Plymouth Avenue to Burnside Avenue and at various locations throughout San Francisco. Work activities to be performed on this project include, but are not limited to:

  • General Roadway and Pavement Demolition

  • Installation of new 12-Inch and 18-Inch Sanitary Sewer Line and New Side Sewer Services.  Note, temporary service interruptions will be required as new connections are made.

  • Installation of concrete street at the Mangels Avenue / Edna Street intersection.  Note, temporary access interruptions will be required as new street is installed.

  • Installation of new sidewalk, driveways, curb / gutter, and ADA curb ramps.  ADA Curb Ramps will be installed at the following locations along the Mangels Corridor:

    • All ramps at Colon Avenue, Valdez Avenue, Hazelwood Avenue, Brentwood Avenue, Ridgewood Avenue, Gennessee Street, and Detroit Street on Mangels Avenue. All ramps at Saint Elmo Way and El Verano Way.

  • The removal / replacement of roadway concrete base and asphalt surface pavements the full width and length of Mangels Avenue from Plymouth Avenue to Burnside Avenue, Saint Elmo Way from Monterey Boulevard to Yerba Buena Avenue, and Miramar Avenue from Monterey Boulevard to Northwood Drive.

Project Locations

Eureka Street: Eureka Street (Map) (Construction is complete)
Between 17th Street and 23rd Street
Grand View Avenue: Grand View Avenue from Clipper Street to Market Street (MapConstruction is currently in progress)
Romain Street from Market Street to Douglass Street
Grand View Terrace from Grand View Avenue to End
Douglass Street from 21st Street to Corwin Street
Corwin Street from Douglass Street to End.
Mangels Avenue: Mangels Avenue from Plymouth Avenue to Burnside Avenue (Map) (Construction is currently in progress)
Saint Elmo Way from Monterey Boulevard to Yerba Buena Avenue
Miramar Avenue from Monterey Boulevard to Northwood Drive 
Diamond Street: Diamond Street from Hiliritas Avenue to Moreland Street (Map) (Construction is currently in progress)
Hiliritas Avenue from Arbor Street to Diamond Street
Moreland Street from Diamond Street to Farnum Street 

Project Updates:

02/08/18: Crews have completed parking strip work and paving activity on Eureka Street between Market and 23rd Street. Crews will next conduct a final inspection of the roadway. Once approved, SFMTA will install final traffic striping. Crews will also return at a later date to install a water cistern ring at 21st and Eureka. That installation date is TBD. 

On Grand View Avenue, crews have begun sewer main and manhole installation work between 21st and 22nd streets. Crews are excavating through solid rock, so progress has been greatly reduced. Crews anticipate working in the area through the end of the month and through mid-March to complete sewer and ADA curb ramp work. 

On Mangels Avenue, crews are continuing with side sewer work between Gennessee and Ridgewood streets. Crews anticipate sewer main installation between Nordhoff and Congo streets starting the week of February 19th. 

On Diamon Street, crews continue to work on ADA curb ramp installation work and will continue curb ramp and sidewalk work through the week of February 19th.  Roadbase restoration work on Diamond is anticipated to begin the week of February 26th. 

On Hiliritas Avenue, crews completed 1/2 of the concrete street installation work. Crews will begin work on the next 1/2 of the street starting on Monday, February 12th. Crews will demo the existing street and then pour the new concrete street, followed by a 10-day curing period. 


01/22/18: Crews have begun roadway grinding work on Eureka Street in preparation for final roadway paving. Crews previously laid down temporary pavement and will grind that and the roadway down to make room for the final layer of asphalt. Crews will pave on a block by block basis on Eureka, starting with paving between 23rd and 20th on 01/23 and from 20th to Market on 01/26. Paving work is anticipated to last through the end of the week. Crews DO NOT anticipate working Wednesday 01/24/18 in anticipation of a rain day. 

Crews will then adjust street castings as needed and Public Works will conduct a final inspection of the roadway. Once approved, SFMTA will complete final traffic striping and will demobilize any remaining equpiment and materials from the area, at which point, construction activity on Eureka Street will be complete. 

On Grand View Avenue, crews anticipate resuming sewer main installation work between 21st and 22nd startin gon Monday 1/29. 

Crews will also begin ADA curb ramp installation work on Diamond Street starting Monday, 1/29 and anticipated to continue throught mid-February 2018. Crews will also begin installation of a new concrete street on Hiliritas Avenue starting Monday, 1/29 and anticipated to continue through the end of February 2018.
 

01/16/18: On Eureka Street, crews are wrapping up road base repairs and anticipate completing road base work on Friday, 01/19. Crews will begin paving preparation work (roadway grinding) on Eureka Street between Market and 23rd Street, starting Monday 01/22 through Friday, 01/26. As crews grind the street, crews will follow and complete final roadway paving. Paving will begin Tuesday 01/23 and is anticipated to continue through 02/02. Once SFMTA reviews and approves paving work, crews will paint on final traffic striping, which will be done a few weeks after final paving work is complete. 

Crews will resume sewer work on Grand View Avenue starting the week of 01/22. Crews will complete side sewer repairs on Grand View between 24th and 25th on 01/22 and 01/23 and will begin sewer main and manhole installation work on Grand View Avenue between 21st and 22nd streets starting Wednesday, 01/24 and anticipated to continue through the end of February. 

Crews will begin curb ramp work on Diamond Street starting Thursday, 01/18. Work is anticipated to continue through the end of February.  

Archived Project Updates

Streets & Streetscapes
STATUS In Progress
Location
Eureka Street, Grand View, Mangels Avenue and Diamond Street
Start Date December 2016
Completion Date February 2018
Budget
$8,200,000
Project Manager
Ramon Kong
Project Team

San Francisco Public Works
San Francisco Public Utilities Commission

Con-Quest Contractors, Inc. 

Contact
Coma Te
Phone
(415) 558-5283