Main menu

  • Brannan St.

Brannan Street Pavement Renovation and Sewer Replacement Project

Project Update: June 2019
Crews continue sidewalk work along the southside of Brannan Street between 8th Street and 9th Street. The sidewalk work at this location will be completed soon. 

The contractor also continues street base replacement work on Brannan Street. This phase of work requires the contractor saw-cut portions of the roadway, remove the broken concrete base, and pour back fresh concrete. Replacing the damaged street base now will help prolong the life of the new asphalt once the street is repaved. 

Upcoming Grinding and Paving
On Saturday June 22, 2019, crews are scheduled to grind and pave the Brannan and 6th streets intersection. The grinding and paving work will be completed in one day. The work is being performed on the weekend due to the large volume of traffic entering and exiting the freeway.

Vehicles traveling westbound will be detoured at the 5th Street intersection and eastbound traffic will be detoured at the 7th Street intersection. Local traffic will still be allowed access. 

The last section of grinding and paving work will be on Brannan Street between 8th Street and Division Street. This section has been scheduled for Monday July 8th and Tuesday July 9th.

******   Sign Up for Updates HERE.   ******

Project Description
The Brannan Street Pavement Renovation and Sewer Replacement Project will include sewer main replacement along several blocks of Brannan Street. The sewer work phase will typically take approximately 1-2 months to complete per block however not all blocks will include sewer main replacement work. This project will also include the installation of new curb ramps, replacement of broken concrete street base, fiber conduit work and repaving of the blocks listed below. San Francisco Public Works will manage the project during construction and will work with Trinet Construction Inc., the prime contractor for the project to complete the project on time and on budget. The entire project is estimated to take a year to complete.

Traffic may be temporarily delayed at times as a result of lane closures necessary to perform the work. "No Parking" and "Tow-Away" signs will be posted 72 hours in advance to alert motorists of upcoming parking restrictions. Access to private and/or commercial buildings will be maintained at all times. Please observe parking and traffic signage and allow extra travel time in case of traffic delays during construction.

Project limits:
Brannan Street between Division Street to The Embarcadero

Scope of Sewer Work:

  • Brannan St. between Ritch and 3rd streets
  • Brannan St. between 3rd and 2nd streets
  • Brannan and Harriet St. intersection
  • Brannan St. between 9th and 8th streets
     

Scope of Paving Work:
Brannan St. between Division Street to The Embarcadero

Work Hours:
Monday through Friday, 8 a.m. – 4 p.m.
Saturday and Sunday, 8 a.m. – 6 p.m. 
*** Please note: Work hours may start earlier or continue later than shown during grinding and paving work. ***

 
 
Pavement and Sewer Renovation
District
Start Date March 12, 2018
Completion Date May 01, 2019
Release Date
Monday, February 5, 2018
Project Team

Trinet Construction, Inc.
(415) 695-7814

For urgent matters after regular business hours, please contact Trinet Project Manager James Leyden at (650) 315-5392.

Contact
Alex Murillo, S.F. Public Works Public Affairs Division
Phone
(415) 558-5296