Main menu

  • Townsend and Clyde intersection
  • 17th and Church intersection

Various Locations Curb Ramps #10

San Francisco Public Works has hired R&S Construction Management, Inc. to construct new curb ramps at intersections throughout San Francisco. This project will include demolishing existing curb ramps & curbs, constructing new, ADA-compliant curb ramps and reconstructing adjacent areas of the sidewalk and curb lane. Work will be taking place at the following intersections:

  • Twin Peaks Boulevard and Crown Terrace - Complete
  • Twin Peaks Boulevard and Graystone Terrace - Complete
  • San Jose Avenue and Broad Street - Complete
  • 17th Street and Church Street - Complete
  • Townsend Street and Clyde Street - Complete

 

Note: Construction schedules, dates and durations are subject to change due to rain, equipment breakdown, unforeseen field conditions, existing utility conflicts, or crew availability.

Although there will be minimal restrictions to on-street parking, this project will not cause any street closures or interruptions in sewer service. During construction, traffic control will be implemented and "No Parking/Tow Away Zone" signs will be posted in active work areas. Local access for Residents, Deliveries and Emergency Services will be provided at all times during work hours. 

PROJECT UPDATE: 2/2/23

Starting on Monday, February 6th, crews will begin working at the intersection of Clyde Street and Townsend Street. The work at this location will include the construction of new curb ramps on either side of Clyde, as well as related traffic routing and sewer work. Barring any unforeseen delays, the work at Townsend and Clyde should take roughly 1-2 weeks. During this time, there will be minimal restrictions to on-street parking on the adjacent blocks to provide adequate space for traffic routing and construction work. A full, accessible path of pedestrian travel will be maintained throughout the construction process.

PROJECT UPDATE: 1/23/23

Starting on Wednesday, January 25th, crews will begin working at the intersection of 17th Street and Church Street. The work at this location will include the construction of new curb ramps at all four corners, as well as related traffic routing and sewer work. Barring any unforeseen delays, the work at 17th and Church should take roughly 4-5 weeks. During this time, there will be minimal restrictions to on-street parking on the adjacent blocks to provide adequate space for traffic routing and construction work. A full, accessible path of pedestrian travel will be maintained throughout the construction process.

Streetscapes
STATUS Completed
Location
Throughout San Francisco
Start Date November 03, 2022
Completion Spring, 2023
Release Date
Friday, October 21, 2022
Project Manager
Edmund Lee
Project Team

San Francisco Public Works

R&S Construction Management, Inc.

Office: (415) 872-9935 

After Hours/Urgent: (415) 872-9935

Contact
Benjamin Peterson
Phone
(628)271-3057