Various Locations Pavement Renovation and Sewer Replacement No. 60

San Francisco Public Works has contracted with Precision Engineering Inc. to install new sewer utilities and renovate the roadway at various locations in San Francisco as part of the Various Locations Pavement Renovation and Sewer Replacement Project No. 60 (VL60). We will be performing this work in the Pacific Heights, Anza Vista, Western Addition, Cathedral Hill, Telegraph Hill, Inner Sunset and Outer Sunset neighborhoods. 

We have inspected the sewer facilities of all the blocks listed below, and will be replacing those that we found to be cracked and/or broken.  Replacing these pipes now will prevent possible collapse of the sewer mains and pavement in the future. Sewer service will not be interrupted during the construction.  

This project will include sewer main replacement, curb ramp installation, street base repairs and repaving. Work hours will vary by location, however, typical working hours are 7 a.m. to 5 p.m. Monday through Friday. Weekend work is allowed but has not been scheduled at this time.

Street resurfacing work will be taking place on the following blocks. Only those in bold will be receiving sewer work as well:

Presidio Avenue from Pacific Avenue to Washington Street - In Progress

Presidio Avenue from Washington Street to Bush Street - In Progress

Presidio Avenue from Bush Street to Sutter Street

Presidio Avenue from Sutter Street to Geary Boulevard

California Street from Broderick Street to Pierce Street

California Street from Pierce Street to Steiner Street

California Street from Franklin Street to Van Ness Avenue

Sacramento Street from Steiner Street to Fillmore Street

Clay Street from Fillmore Street to Webster Street

Buchanan Street from Clay Street to Sacramento Street

Ellis Street from Gough Street to Van Ness Avenue

Eddy Street from Scott Street to Laguna Street

Turk Street from Laguna Street to Van Ness Avenue

O’Farrell Street from Masonic Avenue to St. Joseph’s Avenue

34th Avenue from Ortega Street to Pacheco Street 

Ortega Street from 17th Avenue to 15th Avenue

29th Avenue from Rivera Street to Santiago Street - In Progress

17th Avenue from Rivera Street to Santiago Street

Pacheco Street from Dewey Boulevard to Magellan Avenue

Ulloa Street from the Great Highway to 42nd Avenue - In Progress

Ulloa Street from 19th Avenue to 18th Avenue

Ulloa Street from 16th Avenue to 15th Avenue

39th Avenue from Yorba Street to Sloat Boulevard - In Progress

Telegraph Hill Boulevard from Kearny Street to End 

Construction Updates

7/12/24: Ulloa Street will be Re-Paved between the Great Highway and 42nd Avenue July 16 - July 18

Starting Tuesday, July 16, San Francisco Public Works will be re-paving Ulloa Street from the Great Highway to 42nd Avenue. We expect this work to take 3 days in total to complete. The first step of this work is to grind away the existing asphalt roadway surface. Then, we will re-apply 2 new inches of asphalt to the roadway. It will progress in the following order:

Tuesday 7/16: Grind away existing asphalt and re-pave Ulloa Street from the Great Highway to 46th Avenue

Wednesday 7/17: Grind away existing asphalt and re-pave Ulloa Street from 46th Avenue to 44th Avenue

Thursday 7/18: Grind away existing asphalt and re-pave Ulloa Street from  44th Avenue to 42nd Avenue.

7/9/24: Street Base Repair and Re-Paving on 39th Avenue between Yorba Street and Sloat Avenue starting on Friday, July 12th. 
 
Starting on this date, crews will repair portions of the concrete street base on 39th Avenue between Yorba Street and Sloat Boulevard. Once this work is complete, they will go back and re-pave the entire block. We expect this work to take roughly 3 weeks to complete barring any unforeseen circumstances.
 
6/24/24: Curb Ramp Construction at the Intersection of Presidio Avenue and Pacific Avenue starting on Wednesday, June 26th.
 
On Wednesday, June 26th, our contractor will begin curb ramp reconstruction at the intersection of Presidio Avenue and Pacific Avenue. The first step in this process is to relocate some of the catch basins at this intersection to improve drainage. Then, new ADA-compliant curb ramps will be constructed at each corner of this intersection - 8 ramps in total. Portions of the sidewalk and street adjacent to these new ramps will be reconstructed as well. In total, we expect this work to take four to five weeks to complete.
 
6/18/24: Sewer Main Replacement on 29th Avenue between Santiago and Rivera AND Stree Base Repair on Presidio Avenue between Pacific and Sacramento Starting Monday, June 24th..
 
Starting next Monday, June 24th, our contractor will be replacing the sewer main on 29th Avenue between Santiago Street and Rivera Street. Once the sewer main is replaced, we will then inspect the block's sewer laterals and replace them on an as-needed basis. Sewer laterals are what connect household plumbing to the sewer main. In total, we expect sewer work to take between 3 and 4 weeks to complete on this block. Once all sewer work is complete on this block, it will be fully re-paved. Additional notice will be given prior to re-paving work.
 
At the same time, crews will begin repairing portions of the concrete street base on Presidio Avenue between Pacific Avenue and Sacramento Street. This includes re-constructing the concrete street base in areas that were excavated for recent sewer main replacement, as well as other portions of the street base on blocks where no sewer work has occurred. A majority of this work will be taking place on Presidio between Washington and Clay Streets.
 
6/6/24: Curb Ramp Construction at the Intersection of 45th Avenue and Ulloa Street starting on Monday, June 17th.
 
On Monday, June 17th, our contractor will begin curb ramp reconstruction at the intersection of Ulloa Street and 43rd Avenue. The first step in this process is to relocate some of the catch basins at this intersection to improve drainage. Then, new ADA-compliant curb ramps will be constructed at each corner of this intersection - 8 ramps in total. Portions of the sidewalk and street adjacent to these new ramps will be reconstructed as well. In total, we expect this work to take four to five weeks to complete.
 
5/30/24: Sewer Main Replacement on Presidio Avenue between Jackson and Washington Starting Thursday, June 6th..
 
Starting next Thursday, June 6th, our contractor will be replacing the sewer main on Presidio Avenue between Jackson Street and Washington Street. Once the sewer main is replaced, we will then inspect the block's sewer laterals and replace them on an as-needed basis. Sewer laterals are what connect household plumbing to the sewer main. In total, we expect sewer work to take between 2 and 3 weeks to complete on this block. Work will then be progressing southward on Presidio Avenue throughout the following months.
 
5/9/24: Construction on Presidio Avenue and Ulloa Street starting on Thursday, May 16th..
 
Starting next Thursday, May 16th, our contractor will be replacing the sewer main on Presidio Avenue between Pacific Avenue and Jackson Street. Once the sewer main is replaced, we will then inspect the block's sewer laterals and replace them on an as-needed basis. Sewer laterals are what connect household plumbing to the sewer main. In total, we expect sewer work to take between 3 and 4 weeks to complete on this block. Work will then be progressing southward on Presidio Avenue throughout the following months.
 
Also on May 16th, our crews will begin performing spot sewer work and curb ramp reconstruction at the intersection of Ulloa Street and 43rd Avenue. The first step in this process is to relocate some of the catch basins at this intersection to improve drainage. Then, new ADA-compliant curb ramps will be constructed at each corner of this intersection - 8 ramps in total. Portions of the sidewalk and street adjacent to these new ramps will be reconstructed as well. In total, we expect this work to take four to five weeks to complete.
 
4/24/24: Construction starting in roughly one month. In late May 2024, our contractor will begin sewer main replacement work on Presidio Avenue between Pacific Avenue and Washington Street. Work will then be progressing southward on Presidio Avenue throughout the following months.
 
Street reconstruction and re-paving work will also be starting in late May 2024. Our first location will be Ulloa Street between the Great Highway and 42nd Avenue. 
 
Additional details will be provided as construction start approaches. Residents of these areas will also be receiving notices in the mail from both Public Works and our contractor in the coming weeks.
Pavement and Sewer Renovation
STATUS In Progress
Location
Throughout the Sunset, Presidio Heights, Lower Pacific Heights, Western Addition and Telegraph Hill
Start Spring, 2024
Completion Winter, 2025
Budget
$11.1 Million
Project Manager
Edmund Lee
Project Team

San Francisco Public Works

Precision Enginnering, Inc.

Contact
Benjamin Peterson
Phone
(628) 271-3057