Hunters Point, Central Waterfront and Potrero Hill Area Pavement Renovation and Sewer Replacement Project

San Francisco Public Works has contracted with Esquivel Grading and Paving, Inc. to re-pave the roadway, build new curb ramps, and perform sewer work at various locations in San Francisco as part of the Hunters Point, Central Waterfront and Potrero Hill Area Pavement Renovation and Sewer Replacement Project. 

All of the blocks listed below have been identified as prime candidates for repaving and street base repair due to their current conditions and amount of wear. Reconstructing these streets now will prevent possible damage and deterioration that may pose future safety risks. 

We will also be performing some small-scale sewer work on a handful of these blocks. Most sewer work on this project will be to improve drainage in low laying areas through the construction of new sewer culverts. Work hours will vary by location, however, typical working hours are 8 a.m. to 5 p.m. Monday through Friday. Weekend work is allowed but has not been scheduled at this time.

Street resurfacing work will be taking place on the following blocks. Only those in bold will be receiving sewer work as well:

  • 18th Street from Carolina to Arkansas

    Wisconsin Street from 16th to 17th

    De Haro Street from 15th to 16th

    Rhode Island Street from Mariposa to 18th

    Rhode Island Street from 23rd to 24th

    25th Street from Utah to VermontMinnesota Street from 25th to Cesar Chavez

    Newcomb Ave from Newhall to 3rd

    Mendell Street from Cargo to Newhall

    Hunters Point Boulevard from Evans to Hawes - Starting late June 2024

    Hawes Street from Hunters Point to Innes

    Innes Avenue from Middle Point/Ingalls to Fitch 

    Northridge Road from Harbor to Jerrold/Dormitory

    Earl Street from Kirkwood to Jerrold

    Kirkwood Avenue from Earl to La Salle 

 

Pavement and Sewer Renovation
STATUS In Progress
Location
Various Locations in Hunters Point, Potrero Hill and Central Waterfront Neighborhoods
District
Start Summer, 2024
Completion Spring, 2025
Budget
$6.1 Million
Project Manager
Ramon Kong (628) 271-2581
Project Team

San Francisco Public Works

Esquivel Grading and Paving, Inc.

Contact
Benjamin Peterson
Phone
(628)271-3057