• Water Main Installation

Eureka, Grand View and Mangels Pavement Renovation, Sewer Replacement and Water Main Installation Project

This project will involve the renovation and improvement of Eureka Street between 23rd Street and Market Street, Grand View Avenue between Clipper Street and Market Street, Mangels Avenue from Plymouth Avenue to Burnside Avenue and at various locations throughout San Francisco. Work activities to be performed on this project include, but are not limited to:

  • General Roadway and Pavement Demolition

  • Installation of new 12-Inch and 18-Inch Sanitary Sewer Line and New Side Sewer Services.  Note, temporary service interruptions will be required as new connections are made.

  • Installation of concrete street at the Mangels Avenue / Edna Street intersection.  Note, temporary access interruptions will be required as new street is installed.

  • Installation of new sidewalk, driveways, curb / gutter, and ADA curb ramps.  ADA Curb Ramps will be installed at the following locations along the Mangels Corridor:

    • All ramps at Colon Avenue, Valdez Avenue, Hazelwood Avenue, Brentwood Avenue, Ridgewood Avenue, Gennessee Street, and Detroit Street on Mangels Avenue. All ramps at Saint Elmo Way and El Verano Way.

  • The removal / replacement of roadway concrete base and asphalt surface pavements the full width and length of Mangels Avenue from Plymouth Avenue to Burnside Avenue, Saint Elmo Way from Monterey Boulevard to Yerba Buena Avenue, and Miramar Avenue from Monterey Boulevard to Northwood Drive.

Project Locations

Eureka Street: Eureka Street (Map) (Construction is currently in progress, with construction activity completion anticipated in October 2017)
Between 17th Street and 23rd Street
Grand View Avenue: Grand View Avenue from Clipper Street to Market Street (Map) (Construction activity anticipated to begin in September 2017)
Romain Street from Market Street to Douglass Street
Grand View Terrace from Grand View Avenue to End
Douglass Street from 21st Street to Corwin Street
Corwin Street from Douglass Street to End.
Mangels Avenue: Mangels Avenue from Plymouth Avenue to Burnside Avenue (Map) (Construction activity is anticipated to begin in October 2017)
Saint Elmo Way from Monterey Boulevard to Yerba Buena Avenue
Miramar Avenue from Monterey Boulevard to Northwood Drive 
Diamond Street: Diamond Street from Hiliritas Avenue to Moreland Street (Map)
Hiliritas Avenue from Arbor Street to Diamond Street
Moreland Street from Diamond Street to Farnum Street 

Project Updates:

9/19/17: Crews have completed the majority of water main installation work on Eureka Street and currently working on connection and service change over work on Eureka between 18th and 20th. Crews will begin curb ramp work at various intersecitons on Eureka starting on 10/2. Crews are continuting to work on Corwin Street and anticipate wrapping up sewer work there by 9/27. Crews will begin construction activity on Mangels Avenue starting on 10/2 and will include potholing and sawcutting owrk, sewer main line and manhole installation work. 

8/22/17Crews are currently wrapping up water main installation work on Eureka Street, between 21st and 22nd, this week. Crews will next move onto the intersection of Eureka and 22nd to continue 16” and 8” water main installation work through Friday, 9/15/17. 

The San Francisco Water Department anticipates performing night work on Wednesday, August 30 from 9 PM to 1AM at the intersection of 18th and Eureka to complete water service connection work.

Remaining work on Eureka includes service change over work, ADA curb ramp installation work and roadway paving.

The Grand View Avenue segment is anticipated to begin on Corwin Street starting September 5th, 2017 and followed by the Mangels Avenue segment anticipated to be starting the week of October 2nd, 2017. 

7/25/17: Crews are wrapping up side sewer replacement work on Eureka between 20th-21st streets and are working on grouting manholes and catch basin tramp installation work between Market and 21st streets. Water work is ongoing at various locations on Eureka, including pressure testing between Market & 18th, and between 18th and 19th streets. 8" water main installation work on Eureka between 20th and 21st streets is anticipated to begin the week of 7/31, at Eureka and 21st starting the week of 8/7 and between 21st and 22nd streets starting the week of 8/14. Water connection work is also scheduled to begin starting the week of 8/14. Work remaining on Eureka Street includes: piping and utility connection work, pavement preservation and final roadway paving work and is anticipated to be completed in October 2017

The Grand View Avenue phase of this project is anticipated to begin in September 2017.

The Mangels Avenue phase of this project is anticipated to begin in October 2017

7/14/17Crews on Eureka are currently working on sewer main installation and side sewer replacement work on Eureka between 20th and 21st street. Sewer work at this location is anticipated to continue through 7/21. Crews have completed service change overs for water service on Eureka between 18th and Market and have performed hydrant and 8” water main connection work.  Crews will perform additional water main installation work on Eureka between 18th and 19th, conducting pressure tests and connection work, between 7/20 – 7/21. Water connection and chlorination work will resume on Eureka between Market and 18th on 7/31 and continue through 8/4. 

Construction activity is anticipated to commence on the Grand View Avenue, Romain Street, Grand View Terrace, Douglas Street and Corwin Street phase of the Pavement Renovation, Sewer Replacement and Water Main Installation Project starting in September 2017. Impacted residents will receive a notice of upcoming construction approximately 10 days prior to the start of construction. Additional details and updates will be posted on this webpage as it becomes available.

05/22/17 - 06/01/17: Crews are currently working on sewer main installation work on Eureka between 20th and 21st streets and have begun water main installation work on Eureka between 18th and 20th streets, which is anticipated to continue through the week of 06/05/17.

04/24/17: Construction Schedule Update - Construction activity on Eureka Street is anticipated to resume on Monday, May 1, 2017. 

04/06/17: Construction Schedule Update - Crews will send out an updated notice 10 day prior to work starting and will post "No Parking"/Tow-Away signs in the project area at least 72 Hours prior to work starting. Crews have completed sewer main installation work on Eureka between 19th and 20th streets and will continue next week with sewer main installation work at the intersection of Eureka and 20th Street and water main installation work between 18th and 19th streets. 

03/24/17: Construction Schedule Update - Work on Grand View Avenue, Romain Street, Grand View Terrace, Douglas Street and Corwin Street is now anticipated to begin the week of April 10, 2017Crews will send out an updated notice 10 day prior to work starting and will post "No Parking"/Tow-Away signs in the project area at least 72 Hours prior to work starting. 

03/13/17: Construction is anticipated to begin on Grand View Avenue, Romain Street, Grand View Terrace, Douglas Street and Corwin Street the week of March 27, 2017Please refer to and observe "No Parking"/Tow-Away signs in the project area. Crews will post these signs at least 72 Hours prior to work starting. Street parking may be unavailable during different phases of construction, but access to private or commercial buildings and pedestrian pathways will be maintained at all times, however delays may be possible. Crews are currently performing sewer main installation work on Eureka Street between 19th and 20th streets and have completed sewer main installation on Eureka between 18th and 19th streets. Crews will also continue to perform cured in place sewer liner installation work on Eureka between 17th and Market streets through the end of March. 

01/31/17: Construction is anticipated to begin at Eureka Street on February 06, 2017. Please refer to and observe "No Parking"/Tow-Away signs in the project area. Crews will post these signs at least 72 Hours prior to work starting. 

01/20/17: Construction is anticipated to begin at Eureka Street in early 2017 and activity will consist of: Resource mobilization to job site, project sign installation, pothole and saw cutting and installation of 18" and 12" sewer mains and manholes. Residents in the impacted work area will receive a notice 10 days prior to work starting with additional information from the contractor.

Streets & Streetscapes
STATUS In Progress
Location
Eureka Street, Grand View, Mangels Avenue and Diamond Street
Start Date December 2016
Completion Date February 2018
Budget
$8,200,000
Project Manager
Ramon Kong
Project Team

San Francisco Public Works
San Francisco Public Utilities Commission

Con-Quest Contractors, Inc. 

Contact
Coma Te
Phone
(415) 558-5283