The Second Street Improvement Project stretched from downtown San Francisco to SOMA.
The project, located on Second Street between Market and King streets, included widened sidewalks between Harrison and Townsend streets; one-way cycle track bicycle facilities in the northbound and southbound directions; transit boarding islands at most transit stops along with planted medians; Americans with Disabilities Act (ADA)-compliant curb ramps; new street trees; site furnishings (trash receptacles, bike racks, benches, and pedestrian lighting); upgrades to the traffic signal system; and a repaved street, curb-to-curb.
The majority of major construction activity on Second Street has been completed.
Construction Schedule
Construction Updates
01/22/21: Overhead utility undergrounding work is also still pending, and being managed directly by PG&E and property owners. On Monday, January 25, 2021, roadway crews will be on site to grind and repave portions of the cycle track and roadway on the block of Second Street between Bryant and Brannan streets to address roadway elevation issues. SFMTA paint shop crews are also in the process of applying final traffic striping, crosswalk and bike lane markings on Second Street, between Folsom and Townsend streets. Crews will continue to work on applying final traffic, crosswalk and bike lane markings over the coming weeks.
09/23/20: Upcoming Paving Activity: Crews will soon begin grinding and paving activity on the final block of the Second Street Improvements Project, between Harrison and Bryant streets. Roadway grinding activity will occur on Thursday 9/24 and on Friday, 9/25 in the bikeway/cycle track and roadway and will be followed by paving activity on Saturday 9/26. Some paving activity in the bikeway may occur sooner. Once paving activity is complete, crews will install temporary roadway striping. Final traffic striping will be applied by SFMTA paint shop crews once the roadway is inspected and approved. (Please note, there may be a slight pause of a few weeks to a few months after final paving activity before final traffic striping is applied depending on inspection, approval times and paint shop crew availability.)
09/16/20: The week of September 14, crews will work on concrete street base and grind and pave 2nd Street, between Brannan and Bryant streets, will also continue tree, plant and irrigation installation work between King and Brannan streets, install ADA curb ramps at the NE corner of 2nd and Harrison Street, work on bicycle track and irrigation work along the west side of 2nd Street between Stillman and Harrison and install a bus island at the SW corner of 2nd and Harrison Street and continue concrete street base work on 2nd between Bryant and Harrison streets. Crews also plan to work on Saturday, September 19 on 2nd Street, between Bryant and Harrison streets to continue concrete street base work. The week of September 21, crews will continue tree, plant and irrigation installation work between King and Brannan streets, will begin concrete street base work at the intersection of 2nd and Harrison, will begin ADA curb ramp work at the NW corner of 2nd and Harrison and will continue concrete street base work on 2nd Street between Bryant and Harrison. The week of September 28, crews will continue tree, plant and irrigation installation work between King and Brannan streets, will begin installation of tree well granite pavers on 2nd Street, between Brannan and Harrison, will continue concrete street base work on 2nd Street between Bryant and Harrison. The week of October 5, crews will continue tree, plant and irrigation installation work between King and Brannan streets, will continue installation of tree well granite pavers on 2nd Street, between Brannan and Harrison, and will begin grinding and paving work on 2nd Street between Bryant and Harrison streets.
Project Update Archive
Community Meetings
Construction Open House was held on November 30, 2017, 6-8PM at SPUR, 654 Mission Street. Thank you to all those that attended to learn more about the upcoming construciton activity on Second Street!
Community Presentation - Meeting Four - 5/23/2013
Presentation boards
Community Presentation - Meeting Three - 11/28/2012
Presentation boards:
Survey Results
Community Presentation - Meeting Two - 10/20/2012
Presentation Boards:
Bike Lane Option: Cross Section and Typical Intersections; Plan View
Center Turn Lane with Bike Lanes: Cross Section and Typical Intersections; Plan View
One-Way Cycletracks: Cross Section and Typical Intersections; Plan View
Two-Way Cycletrack: Cross Section and Typical Intersections; Plan View
Brief comparison of the design concepts
Survey used to collect feedback from Community meeting two.
Community Presentation - Meeting One - 5/2/2012
San Francisco Public Works
Municipal Transportation Authority (SFMTA)
SF Planning Department
San Francisco Transportation Authority