Public Safety Building

The Public Safety Building is officially open and fully operational as of April 2015.
 

The LEED Gold-certified police headquarters, located in Mission Bay, replaced the more than 50-year-old location at the Hall of Justice (850 Bryant Street) with a seismically-resilient building that accommodates the needs of a modern police force. It also replaced the Southern District Police Station. 
 

Minna Natoma Streetscape Project

Project Status

 

The Minna–Natoma Streetscape Project continues to move forward, with several important milestones completed as the project prepares for its next major phase.

 

The construction team has successfully completed sewer improvement work along Natoma Street, marking a significant achievement for the project. In addition, all project redesigns have been completed and approved, and the artwork planned for the streetscape has also received final approval.

 

Market Octavia Living Alleys

Project Update (August 2026)

This project is almost complete. Only some minor punch list work remains. 
 

Project Description
The Market and Octavia Living Alleys project aims to create a public realm that strengthens the community, creates a sense of identity and makes a more useful, safe and attractive neighborhood.

Better Market Street

A renewed Market Street will anchor multiple downtown neighborhoods and link public open spaces. It will also connect the city’s Civic Center with cultural, social, convention, tourism, and retail destinations, as well as the Salesforce Transit Center, the regional transit hub. The vision is to make Market Street a place where people will want to stop and spend time, meet friends, people-watch while sitting in a café, or just stroll and take in the urban scene.

 

Brannan Street Pavement Renovation and Sewer Replacement Project

Project Update: June 2019
Crews continue sidewalk work along the southside of Brannan Street between 8th Street and 9th Street. The sidewalk work at this location will be completed soon. 
 

The contractor also continues street base replacement work on Brannan Street. This phase of work requires the contractor saw-cut portions of the roadway, remove the broken concrete base, and pour back fresh concrete. Replacing the damaged street base now will help prolong the life of the new asphalt once the street is repaved.