Main menu

  • street level view of the Dorantes and Montalvo intersection
  • street level view of the Pioche and Harvard intersection

As-Needed Curb Ramp Construction for Street Resurfacing Program No.7

San Francisco Public Works has hired Precision Engineering, Inc. to construct new curb ramps at intersections throughout San Francisco. This project will include demolishing existing curb ramps & curbs, constructing new, ADA-compliant curb ramps and reconstructing adjacent areas of the sidewalk and curb lane.Work will be taking place at the following intersections:

  • Castenada Avenue and Ventura Avenue - complete
  • Santa Rita Avenue and Sotelo Avenue - complete
  • Cortes Avenue and Dorantes Avenue - complete
  • Montalvo Avenue and Dorantes Avenue - complete

Once curb ramp work is completed at all listed locations, the contractor will then begin re-paving the adjacent intersections. The start dates and sequencing of this re-paving work will be added to this page as soon as they are confirmed by Public Works and our contractor. Once all curb ramp and paving work is completed at the above locations, crews will then begin constructing curb ramps at a new set of locations, listed below:

  • Ingalls Street and Fitzgerald Avenue - complete
  • Brunswick Street and Roemer Way - complete
  • Pioche Street and Harvard Street - complete
  • Drake Street and Winding Way - complete
  • Bacon Street and Cambridge Street -complete

Note: Construction schedules, dates and durations are subject to change due to rain, equipment breakdown, unforeseen field conditions, existing utility conflicts, or crew availability.

Although there will be minimal restrictions to on-street parking, this project will not cause any street closures or interruptions in sewer service. During construction, traffic control will be implemented and "No Parking/Tow Away Zone" signs will be posted in active work areas. Local access for Residents, Deliveries and Emergency Services will be provided at all times during work hours. A full, accessible path of pedestrian travel will be maintained throughout the construction process.

Construction Updates:

7/12/23:

As of the end of June, all curb ramp construction, sewer replacement, and paving work at all locations listed above is complete. The only work that remains to be done is the installation of a handrail next to the newly-constructed curb ramp at the intersection of Drake Street and Winding Way. This handrail is currently being fabricated, and will be installed by the end of July. 

5/15/23:

Starting today, May 15th, Public Works will be constructing a new, ADA compliant curb ramp at the southwest corner of the Brunswick Street and Roemer Way intersection. We expect this work to take 3-5 days to complete.

Starting on Thursday, May 18th, Public Works and its contractor Precision Engineering, Inc. will be constructing new, ADA compliant curb ramps at two intersections: Harvard Street and Pioche Street, as well as Drake Street and Winding Way. If we experience no unforeseen delays due to weather or equipment breakdown, we expect work at Harvard and Pioche take about two to three weeks complete, and work at Drake and Winding to take three to four weeks to complete.

None of this work will require any street closures, although there will be some restrictions to street parking near the work area. A pedestrian path of travel will be maintained throughout this project.

4/24/23: Starting on Monday, May 1st, Public Works and its contractor Precision Engineering, Inc. will be constructing new, ADA compliant curb ramps at the intersection of Ingalls Street and Fitzgerald Avenue. We expect this work to take about two weeks complete if we experience no unforeseen delays due to weather or equipment breakdown. The work will progress in the following sequence:

 
The week of May 1st: work will be taking place at the  Northeast and Southwest corners of Fitzgerald and Ingalls.
 
The week of May 7th: work will be taking place at the Northwest and Southeast corners of Fitzgerald and Ingalls.
 
This work will not require any street closures, although there will be some restrictions to street parking near the work area. A pedestrian path of travel will be maintained throughout this project.
Pavement and Sewer Renovation
STATUS Completed
Location
Throughout San Francisco
Start Date November 07, 2022
Completion Date July 31, 2023
Release Date
Wednesday, January 11, 2023
Project Team

San Francisco Public Works

Precision Engineering, Inc.

Office: (415) 621-4882

Urgent/After Hours: (415) 760-8744

Contact
Benjamin Peterson
Phone
(628)271-3057