• Howard street -looking east from 2nd street
  • Howard Street rendering 1 cross walk striping
  • Howard Street rendering 2 busy sidewalks

Transbay Howard Streetscape Improvement Project

July 2026 

 

 

San Francisco Public Works has hired Esquivel Grading and Paving, Inc. to perform a variety of infrastructure improvements along Howard Street between 4th Street and the Embarcadero.  The Howard Transbay Streetscape Improvement Project has begun and we have been coordinating prep-work such as staging, traffic-control and roadway potholing (for underground utilities). .  The construction scheduled sequencing will start at the Embarcadero and work west toward 4th Street. 


This project involves many different infrastructure improvements, including the construction of a new, protected two-way bicycle lane, reconstructed curb ramps and sidewalks, streetscape elements like trees, benches and bicycle racks, new and improved traffic signals, new roadway and pedestrian lighting, and improvements to transit infrastructure.

 

The SF Transbay Howard Streetscape Improvements Project is entering its next phase of construction. As crews continue potholing and underground conduit installations, additional work will take place June 29 through August 21, 2026, at the intersections of 3rd & Howard Streets and 4th & Howard Streets. Construction activities have been scheduled to coordinate with events at the Moscone Center whenever possible.

 

Upcoming Construction Week of June 29, 2026

 

Crews will be performing:

  • Underground electrical conduit installation
  • Emergency Firefighting Water System (EFWS) improvements
  • Sewer infrastructure work, as needed
  • New curb and gutter construction
  • Traffic signal conduit, pull box, and foundation installation
  • Roadway base improvements

 

 

3rd & Howard Street

Work includes underground utility upgrades, curb and gutter construction, roadway improvements, and conduit installation to support future traffic signals and streetscape enhancements.

 

 

4th & Howard Street

Construction will focus on EFWS improvements, utility relocations, roadway upgrades, and traffic signal infrastructure. Additional curb and gutter work may be completed at the southeast corner, depending on field conditions.

 

 

What to Expect

During construction, you may experience:

  • Temporary lane closures
  • Sidewalk and crosswalk detours
  • Construction noise during permitted work hours
  • Temporary pedestrian route changes

 

Access to businesses, residences, and transit services will be maintained whenever possible. Construction schedules are subject to change due to weather, utility coordination, or field conditions.

We are aware of the inconvenience caused by construction and apologize in advance. We will do everything possible to minimize the impact of our activities on your neighborhood.  

If you have concerns (scheduled deliveries, construction questions, accessibility needs, and access) please contact Public Works' Public Affairs representative Dadisi Najib.

 

Your cooperation will help this project be a success for your neighborhood and the City of San Francisco.  Thank you in advance for your understanding and cooperation.

 

SIGN UP HERE FOR CONSTRUCTION UPDATES

 

Learn more about the
project design at:
SFMTA.com/TransbayHoward

Status
In Progress
Location
Howard Street between Fourth Street and the Embarcadero
Districts
District 6
Start
Winter, 2026
Completion
Fall, 2028
Budget
$19.5 million
Client
SFMTA
Project Manager
Trent Tieger
Project Team

Contractor, Esquivel Grading and Paving, Inc.

tel-  After-hours or Urgent 24/7 contact: (415) 354-4870 

Contact
Dadisi Najib