• Brannan St.

Brannan Street Pavement Renovation and Sewer Replacement Project

Project Update:
The contractor is tentatively scheduled to start construction in mid-March 2018. We will provide updates once the start date has been finalized. Sign Up for Updates HERE.

Project Description
The Brannan Street Pavement Renovation and Sewer Replacement Project will include sewer main replacement along several blocks of Brannan Street. The sewer work phase will typically take approximately 1-2 months to complete per block however not all blocks will include sewer main replacement work. This project will also include the installation of new curb ramps, replacement of broken concrete street base, fiber conduit work and repaving of the blocks listed below. San Francisco Public Works will manage the project during construction and will work with Trinet Construction Inc., the prime contractor for the project to complete the project on time and on budget. The entire project is estimated to take a year to complete.

Traffic may be temporarily delayed at times as a result of lane closures necessary to perform the work. "No Parking" and "Tow-Away" signs will be posted 72 hours in advance to alert motorists of upcoming parking restrictions. Access to private and/or commercial buildings will be maintained at all times. Please observe parking and traffic signage and allow extra travel time in case of traffic delays during construction.

Project limits:
Brannan Street between Division Street to The Embarcadero

Scope of Sewer Work:

  • Brannan St. between Ritch and 3rd streets
  • Brannan St. between 3rd and 2nd streets
  • Brannan and Harriet St. intersection
  • Brannan St. between 9th and 8th streets
     

Scope of Paving Work:
Brannan St. between Division Street to The Embarcadero

Work Hours:
Monday through Friday, 8 a.m. – 4 p.m.
Saturday and Sunday, 8 a.m. – 6 p.m. 
*** Weekend work is allowed however none has been scheduled at this time. ***

 
 
Streets & Streetscapes
District
Start Date March 2018
Completion Date February 2019
Release Date
Monday, February 5, 2018
Project Team

Trinet Construction, Inc.
(415) 695-7814

For urgent matters after regular business hours, please contact Trinet Project Manager James Leyden at (650) 315-5392.

Contact
Alex Murillo, S.F. Public Works Public Affairs Division
Phone