• corner of Haight and Ashbury

Haight Street and Hayes Street

Project Update

This week
- The contractor continues bus pad/bulb-out work at the southeast corner of Divisadero and Haight and also at the southeast corner of Fillmore and Haight. Once the bus pads have been poured, the area will remain closed off for an additional 10 days to allow proper curing of the concrete. We want to ensure the concrete has met the necessary strength before traffic is allowed on to it. 
- Crews are also busy installing curb ramps and/or bulb-outs at the Haight & Pierce, Haight & Steiner and Haight & Webster intersections. 
- Water main work continues at the Scott & Haight intersection. 
- The contractor also resumes the installation of the sewer laterals along Hayes Street between Webster and Fillmore streets. 
 
Week of September 18, 2017
- The bus pad, curb ramp and bulb-out work will continue along Lower Haight. 
- The contractor will continue sewer culvert work at the Haight & Webster and also at the Haight & Fillmore intersections. The culvert work is expected to take about a week to complete at these two intersections. 
- Crews are scheduled to begin water service connection work on Haight Street, between Fillmore and Broderick streets.
 
*** Please Note:  The schedule is subject to change due to rain, equipment breakdown, unforeseen field conditions, etc. Please see the posted "no parking" barricades for exact parking restrictions. Parking restrictions may vary per block. ***
 
 
Project Information
The project limits are Haight Street from Ashbury Street to Laguna Street and Hayes Street from Clayton Street to Market Street. There are several blocks included in this project. It may be weeks or months before we reach your block.
 
The scope of work will include sewer main and water main replacement work, traffic and pedestrian signal work, curb ramp and bulb-out work, bus pad and bus bulb work, concrete street base repairs and repaving along Haight and Hayes streets. Not all blocks listed will include sewer main and/or water main replacement work.
 
During sewer main replacement, sewer service will not be interrupted. Please continue to use your household plumbing as usual. However, when the San Francisco Water Department (SFWD) makes final water service connections there may be a temporary interruption to water service. Final tie-in work is traditionally done overnight to minimize disruptions to water service. Typically, there's less demand for water service overnight. SFWD will notify you in advance of any overnight tie-in work or interruptions to water service.
 
 
 

 

Streets & Streetscapes
STATUS In Progress
Location
Haight Street from Ashbury Street to Laguna Street and Hayes Street from Clayton Street to Market Street.
District
Start Date April 2015
Release Date
Thursday, February 18, 2016
Project Team

For after-hours or urgent issues, please call Marty Murphy at Ghilotti Bros., Inc.: 415-454-7011 or 415-760-0592.

Contact
Alex Murillo
Phone
(415) 558-5296