Main menu

  • Chestnut Street
  • Proposed Detail: Broderick to Divisadero
  • Proposed Detail: Steiner to Fillmore
  • Proposed Detail: Scott to Pierce

Chestnut Street Renovation

Project Update
The contractor began work on this project in late May 2017. Crews are currently working on installing new curb ramps at the Broderick, Divisadero, and Scott streets intersections. The curb ramp work will typically take 3-4 weeks to complete at each intersection. 
 
Project Description
San Francisco Public Works has contracted Bauman Landscape and Construction, Inc., to complete work on the Chestnut Street Pavement Renovation and Muni Forward Project. The work to be performed will be on Chestnut Street between Lyon Street and Van Ness Avenue and also on Fillmore Street near the Chestnut Street intersection. The scope of work will include; curb ramps and transit bulbs, bus pads, catch-basin relocation, some sewer lateral replacement, Auxiliary Water Supply System work (AWSS), Muni Overhead Contact System (OCS) work, traffic signal work, street base repairs and repaving.
 
The overall project is anticipated to take 18 months to complete. However, due to the scope of work and span of the project, it may be weeks or months before we begin construction on a block.
 
Chestnut Street, between Divisadero and Pierce streets, will not be repaved curb-to-curb as part of this project. Those blocks are in good condition however we'll still need to perform localized base/paving repairs. These blocks will include some of the aforementioned work. Also, Chestnut Street between Franklin St. and Gough St. will not be repaved as part of this project. That block was repaved a few years ago and is in good condition. 
 
Project Limits
The project limits are Chestnut Street from Lyon Street to Van Ness Avenue.

 



 

Streets & Streetscapes
STATUS In Progress
District
Start Date May 2017
Completion Date November 2018
Release Date
Monday, April 17, 2017
Budget
$4,600,000
Project Manager
Amy Lam
Project Team

Bauman Landscape and Construction, Inc. 

San Francisco Public Works

Contact
Alex Murillo, Public Affairs
Phone
415-558-5296
Download Project Files
Proposed Project Details