Public Works will consider improvements at the intersection of Geary Boulevard and Park Presidio Boulevard.  This project aims to provide a safer and more inviting environment for Muni passengers, pedestrians, runners, and vehicular traffic at the intersection of Geary Boulevard and Park Presidio Boulevard. Our goal is to design and construct improvements and features that reflect the needs of the community and reinforce neighborhood identity.

We are conducting outreach to Richmond District residents, businesses, neighborhood groups and others.  Our goal is to design and construct improvements and features to reflect the desires of the community most impacted while reinforcing the neighborhood identity. Let us know what you think about these potential improvements.  Participate in our survey.

MEJORAS EN LA INTERSECCIÓN DE GEARY Y PARK PRESIDIO  | БЛАГОУСТРОЙСТВО ПЕРЕКРЕСТКА БУЛЬВАРОВ ГИРИ И ПАРК ПРЕСИДИО  |  GEARY 及 PARK PRESIDIO 改善工程

Geary Boulevard provides one of the City’s most convenient ways to get from Ocean Beach to the Civic Center area and beyond.  Park Presidio Boulevard connects 19th Avenue to the Golden Gate Bridge.  This highly traveled intersection is used by vehicular traffic, Muni buses, pedestrians, bike riders and runners, residents and visitors.

Please participate in our survey.  The survey will be available through March, 2017.  
Get On Our Mailing List and receive survey results, meeting information and project updates. 

Potential Gateway Planting Improvements

Potential Sidewalk and Seating Improvements

Rendering  - Potential Improvements Plan         Photos - Existing Conditions

Poster - Community Outreach / Project History

 

Streets & Streetscapes
Location
Geary Blvd and Park Presidio Blvd Intersection
District
Project Manager
Shannon Cairns (415) 581.2576
Project Team

SF Public Works
SF Municipal Transportation Agency
SF Recreation and Parks Department

 

Project Schedule
Community Planning/Outreach
February through March 2017
Design
September 2016 through August 2017
Contract Award
August 2017
Construction
January through May 2018