• Masonic Avenue Streetscape Improvement Project rendering

Masonic Avenue Streetscape Improvement Project

Project Update - August 7, 2017
 
Temporary Paving 
Our contractor is scheduled to perform localized grinding and paving along portions of Masonic Avenue. The City and contractor have identified areas of the roadway that are uneven and could use some attention. Although the paving work is temporary, it’ll improve drivability along Masonic Avenue until final paving is scheduled. Final paving won’t happen until 2018 since we still have several phases of work that remain. The entire project is scheduled to be complete in Spring 2018. 
 
Curb-ramp Work
Curb ramp work continues on Masonic Avenue between Fell and Fulton streets. This type of work will continue for the foreseeable future. 
 
Sewer Work
The mainline and lateral work is complete along Masonic Avenue however some catch-basin work remains.
 
Water Work
The contractor continues water main installation work between Ewing Terrace and Geary Blvd. When the San Francisco Water Department (SFWD) schedules final water service connection work, there may be a temporary interruption to water service. Final tie-in work is traditionally done overnight to minimize disruptions to water service. Typically, there's less demand for water overnight. Change-over connections are typically performed during daytime operations. SFWD will notify you in advance of any overnight tie-in work or interruption to water service. 
 
Electrical Work
The contractor has begun installing pole foundations and electrical conduits for new street lighting near Fell Street. 
 
*** Please Note:  The schedule is subject to change due to rain, equipment breakdown, and/or unforeseen field conditions. Please see the posted "no parking" barricades for exact parking restrictions. Parking restrictions may vary per block. ***
 

Sign up here to get email about project updates.

Work Hours
Monday to Friday, 7 AM to 5 PM
Saturday & Sunday, 8 AM to 7 PM (Weekend work is allowed however none is scheduled at this time)

Project Information
The Masonic Avenue Streetscape Improvement Project, between Geary Boulevard to the north and Fell Street to the south, will provide improvements for pedestrians, bicyclists, motorists and transit riders. The goal of this project is to safely and efficiently accommodate the needs of all roadway users. The proposed improvements are the result of a planning process among Public Works, the Planning Department, SFMTA and Masonic Avenue residents and businesses.

--------------------------------------

Masonic Avenue: Proposed Plan

--------------------------------------

Project improvements include a new landscaped median, new cycle tracks, widened portions of sidewalk, repaving, bus bulb-outs, new street trees and sidewalk planters, new lighting in medians and pedestrian scale lighting on sidewalks and the conversion of a triangular space and road on the southwest corner of Geary Blvd. and Masonic Ave. into a small park and resident traffic only road, which includes public art.

 

Masonic Avenue: typical existing roadway section

 

 

Masonic Avenue: typical proposed roadway section

 

 

Rendering - Masonic Avenue and Turk Street - Option 2

 

Plaza Rendering at Masonic Avenue and Geary Boulevard

 

Presentations

 

Schedule
Community outreach and planning phase: Completed. Conducted 2008-2012.
Design and bid phase: Winter 2014 to Fall 2015.
Construction phase: July 2016 to Spring 2018.

 

Streets & Streetscapes
STATUS In Progress
Location
Masonic Avenue from Geary Boulevard to Fell Street
District
Start Date July 2016
Completion Date April 2018
Budget
$26,000,000
Project Manager
David Froehlich - (415) 558-4041
Project Team

SF Public Works
SFMTA
SFPUC
SF Planning Dept.
Shaw Pipeline, Inc. (contractor)

Contact
Alex Murillo - Public Affairs Officer
Phone
(415) 558-5296
Download Project Files
Masonic Streetscape Factsheet