• Masonic Avenue Streetscape Improvement Project

Masonic Avenue Streetscape Improvement Project

Project Update - 12/20/2016

Sewer Work
The contractor has completed installation of the new sewer main and laterals (connections between the mainline and sidewalk) on Masonic between Fell and Fulton streets. 

Crews continue sewer main replacement work on the Westside of Masonic between Fulton and Turk streets. Once complete, crews will drop back down to the Fulton intersection and start the same process on the east side of the block. The sewer mainline work typically takes about 2 weeks to complete on each side of the block followed by any lateral replacement work. 

Water Work
The contractor continues installation of the 
water main on Masonic Avenue. 

Sign up here to get email about project updates.

Project Information
The Masonic Avenue Streetscape Improvement Project, between Geary Boulevard to the north and Fell Street to the south, will provide improvements for pedestrians, bicyclists, motorists and transit riders. The goal of this project is to safely and efficiently accommodate the needs of all roadway users. The proposed improvements are the result a planning process among Public Works, the Planning Department, SFMTA and Masonic Avenue residents and businesses.

--------------------------------------

Masonic Avenue: Proposed Plan

--------------------------------------

Project improvements include a new landscaped median, new cycle tracks, widened portions of sidewalk, repaving, bus bulb-outs, new street trees and sidewalk planters, new lighting in medians and pedestrian scale lighting on sidewalks, and conversion of a triangular space and road on the southwest corner of Geary Blvd. and Masonic Ave. into a small park and resident traffic only road, which includes public art.

 

Masonic Avenue: typical existing roadway section

 

 

Masonic Avenue: typical proposed roadway section

 

 

Rendering - Masonic Avenue and Turk Street - Option 2

 

Plaza Rendering at Masonic Avenue and Geary Boulevard

 

Presentations

 

Schedule
Community outreach and planning phase: Completed. Conducted 2008-2012.
Design and bid phase: Winter 2014 to Fall 2015.
Construction phase: July 2016 to December 2017.

 

Streets & Streetscapes
STATUS In Progress
Location
Masonic Avenue from Geary Boulevard to Fell Street
District
Start Date July 2016
Completion Date January 2018
Budget
$26,000,000
Project Manager
David Froehlich - (415) 558-4041
Project Team

Public Works
Municipal Transportation Agency
Planning Department

Shaw Pipeline, Inc.

Contact
Alex Murillo - Public Affairs Officer
Phone
(415) 558-5296
Download Project Files
Masonic Streetscape Factsheet