Main menu

  • Aerial view of Sunset Boulevard

Sunset Boulevard Pavement Renovation

Project Update
Starting on Monday, September 09, 2024, and continuing for two weeks, our contractor will begin repaving Sunset Blvd. between Lake Merced Blvd. and Taraval Street. Next week, crews will work in the northbound direction. The following week, crews will work in the southbound direction. 

Motorists using Sunset Blvd. should expect delays and allow extra travel time. The traffic lanes along this portion of Sunset Blvd. will be temporarily reduced from three lanes to one. If possible, please avoid the area and use alternate routes.

The remaining blocks of Sunset Blvd., between Taraval Street and MLK Drive will be paved at a later date. 

The Sunset Boulevard Pavement Renovation Project includes construction of 23 new curb ramps, 20 bus pads, street base repairs and repaving along 44 blocks of Sunset Blvd. Repaving of Sunset Blvd. will include over 12,000 tons of new asphalt and will cover over 880,000 square feet. 

Project Description

San Francisco Public Works has contracted R&S Construction Management to complete the Sunset Boulevard Pavement Renovation Project. The focus of work will be on Sunset Blvd from Martin Luther King Drive to Lake Merced Blvd.

The work will consist of pavement renovation (grinding and paving), concrete road base reconstruction, curb ramp installation, drainage work, bus pad work, bus shelter electrical infrastructure upgrades and traffic signal infrastructure modifications, structural work, traffic control, and all related work.

Construction will begin in February 2024 and is scheduled to continue through late February 2025.Work hours may vary by location, however typical working hours are 7:30 a.m. to 5 p.m., Monday through Friday. Weekend work is allowed but has not been scheduled at this time.

Please note: The schedule may be subject to change due to rain, equipment breakdown or unforeseen field conditions. The planned work may cause traffic delays and necessitate temporary lane closures. Traffic control measures and flaggers will be implemented to minimize disruptions in the roadway. Please allow extra travel time during construction work hours.

Pavement and Sewer Renovation
Location
Sunset Boulevard
District
Start Winter, 2024
Completion Winter, 2025
Release Date
Monday, January 22, 2024
Budget
$7.2 Million
Project Manager
Paul Barradas, (628) 271-2580
Project Team

San Francisco Public Works

San Francisco Municipal Transportation Agency

R&S Construction, Inc. Office - (415) 827-9935, After Hours/Urgent - (661) 863-8782

Contact
Nzuri Stafford
Phone
(628) 271-2246