December 15-21, 2025 Construction Schedule

 

Powell Street/ (Beach St - North Point St)
o Grind and Pave

 

Chestnut Street/ (Jones St – Columbus Ave)
o Grind and Pave

 

Jones Street/ (North Point St – Bay St)
o Grind and Pave

 

Jones Street/ (Lombard St – Greenwich St)
o Grind and Pave
o Concrete Base


Russell Street/ (Eastman St – Hyde St)
o Grind and Pave
o Sidewalk
 

FOLLOWING WEEK (12/22/25 – 12/28/25)- No Construction

 

General Project Description

 

🔧 What Is Grind & Pave?

Grind and pave is a multi-step process that includes:

  1. Grinding – Crews remove the top layer of existing asphalt using specialized equipment. This may result in a rough surface temporarily.

  2. Base & Concrete Work (select areas) – Concrete base repairs, sidewalk work, or related improvements may occur before paving.

  3. Paving – A new layer of asphalt is installed to create a smoother, safer roadway.

  4. Striping & Final Touches – Lane markings and final adjustments are completed following paving.


Work Hours

Monday through Friday: 7:00 AM – 5:00 PM

  • Work may begin as early as 7:00 AM

  • Traffic lane restrictions and tow-away enforcement begin at 8:00 AM

  • Weekend work is allowed; however, none is anticipated at this time

*Schedules may change due to weather or unforeseen conditions.


🚗 Traffic, Parking & Access

  • Temporary lane closures and traffic delays should be expected

  • Driveway access will be maintained, though brief delays may occur while crews work nearby

  • On paving days, vehicles may need to be temporarily relocated to allow asphalt placement and curing

  • Please observe posted “No Parking / Tow Away” signs on construction barricades for exact dates and times

  • Allow extra travel time during construction hours


🔊 Noise & Construction Activity

Residents may notice:

  • Construction noise from grinding and paving equipment

  • Increased truck traffic in the area

  • Dust and vibrations during grinding operations

These impacts are temporary and necessary to complete the work efficiently and safely.


Thank You for Your Patience

We appreciate your cooperation as we complete these important roadway improvements. This work will result in smoother streets, enhanced safety, and longer-lasting pavement for the community.

Thank you for your understanding during construction!

 

Status
In Progress
Start
Spring, 2025
Completion
Winter, 2026
Client
PUC
Project Manager
Paul Barradas
Project Team

Adalbert Cuellar-Franco, Resident Engineer

Contractor: Esquivel Grading and Paving

Carlos Siqueira / Project Manager

PO Box 24-107. San Francisco, CA 94124

Tel: (415) 468-5700   /   Urgent After-hours contact: (415) 354-4870

Email: carlos@esquivel-gp.com

Contact
Dadisi Najib, Public Affairs