Various Locations (VL) #71A
Sign up for E-Newsletter Updates Here
February 17- March 2026 Construction Schedule
Esquivel Grading & Paving (EGP) and JDB crews will be active along Powell Street from Francisco to Filbert over the next 60 days. Work will progress block-by-block and at multiple intersections.
Powell Street/ (Francisco to Filbert)
Concrete Work
Corner ramp and concrete sidewalk work is slated to begin at the following intersections along Powell Street:
- Powell & Chestnut (NE, NW, SE, SW corners)
- Powell & Francisco (SW corner)
- Powell & Lombard (SW corner)
- Powell & Greenwich (NE and SE corners) starting 3/1/26
Additional Improvements
- Powell & Greenwich (NE): Concrete paving operations in progress starting 2/23/26.
- Powell & Francisco: Bus pad installation underway starting 3/1/26
Sewer Work (SW)
- Installation of 10” VCP culvert and catch basins
- Ongoing sewer work at intersections including:
- Powell & Francisco
- Powell & Chestnut
- Powell & Lombard
- Powell & Greenwich (NE/SE corners)
Roadway Improvements
- Base repairs
- Grinding and paving operations
- Work limits include:
- Powell St (Francisco to Filbert)
- Powell St (Filbert to Lombard)
Grant Avenue (Broadway Street to Pine Street)
This work consists of roadway pavement renovation, including roadway base repair, curb ramps and one-block of sewer-replacement.
Sewer work location: Pine St. – California St.
Curb ramp work locations:
- Commercial St. & Grant Ave.
- Vinton Ct. & Grant Ave.
- Pine St. & Grant Ave. (southwest corner)
Roadway work locations:
- Pine St. – California St.
- Sacramento St. – Broadway
Construction duration is two months
starting March 9, 2026, through early May 2026.
Join us at our Community Meeting:
- Tuesday, March 3, 1:30PM – 2:30PM
- Willie “Woo” Wong Clubhouse
(830 Sacramento St., SF, CA 94108)
RSVP: https://forms.office.com/g/p2qPFmzqfm
🔧 What Is Grind & Pave?
Grind and pave is a multi-step process that includes:
Grinding – Crews remove the top layer of existing asphalt using specialized equipment. This may result in a rough surface temporarily.
Base & Concrete Work (select areas) – Concrete base repairs, sidewalk work, or related improvements may occur before paving.
Paving – A new layer of asphalt is installed to create a smoother, safer roadway.
Striping & Final Touches – Lane markings and final adjustments are completed following paving.
⏰ Work Hours
Monday through Friday: 7:00 AM – 5:00 PM
Work may begin as early as 7:00 AM
Traffic lane restrictions and tow-away enforcement begin at 8:00 AM
Weekend work is allowed; however, none is anticipated at this time
*Schedules may change due to weather or unforeseen conditions.
🚗 Traffic, Parking & Access
Temporary lane closures and traffic delays should be expected
Driveway access will be maintained, though brief delays may occur while crews work nearby
On paving days, vehicles may need to be temporarily relocated to allow asphalt placement and curing
Please observe posted “No Parking / Tow Away” signs on construction barricades for exact dates and times
Allow extra travel time during construction hours
🔊 Noise & Construction Activity
Residents may notice:
Construction noise from grinding and paving equipment
Increased truck traffic in the area
Dust and vibrations during grinding operations
These impacts are temporary and necessary to complete the work efficiently and safely.
✅ Thank You for Your Patience
We appreciate your cooperation as we complete these important roadway improvements. This work will result in smoother streets, enhanced safety, and longer-lasting pavement for the community.
Thank you for your understanding during construction!
Adalbert Cuellar-Franco, Resident Engineer
Contractor: Esquivel Grading and Paving
Carlos Siqueira / Project Manager
PO Box 24-107. San Francisco, CA 94124
Tel: (415) 468-5700 / Urgent After-hours contact: (415) 354-4870
Email: carlos@esquivel-gp.com