• street level view of the Clay Street and Grant Street intersection

Various Locations Curb Ramps and Sub-Sidewalk Basements

San Francisco Public Works’ Curb Ramp Program is pleased to announce the Various Locations Curb Ramps and Sub-Sidewalk Basements project.  The project will be implementing various safety and infrastructure improvements, including curb ramp installation, traffic signal improvements, and new pedestrian lighting at Clay Street & Grant Avenue and Sutter Street & Stockton Street. The anticipated duration and scope of work can vary at each location. 

由三藩市工務局無障礙斜坡小組主導本次多個路口無障礙路緣斜坡及人行道地下室加固工程。此工程將會改善多項安全及基礎設施,包括新建無障礙路緣斜坡、升級交通信號燈、分別在企李街與都板街交界路口,以及薩特街與士德頓街交界路口安裝新的照明設備以提高行人安全。根據具體施工地點不同,各工程預計所需時間及施工範圍均有所不同。

To receive regular construction updates, please sign up HERE.  
請點擊此處,登記後即可接收有關此工程的定期進度更新。
 

Construction Updates 工程最新進展

1/28/2025:

Clay & Grant Intersection: Construction resumed after Holiday moratorium. Sub-sidewalk basement work has been completed. The team will start the curb ramp work on the southeast and southwest corners after January 29th celebrations, weather permitting. Curb ramp work is scheduled to be finished in mid-February with final paving to occur after Lunar New Year street market and parade.

Sutter & Stockton: Electrical work is being performed and expected to be completed at the end of January. Curb ramp work will be performed at the median, northwest, southwest, and southeast corners. Work is scheduled to be completed by the end of April.

截至1月28日
企李街及都板街路口:節日後施工恢復正常。人行道地下室及路面工程已完工。在農曆新年(1月29日)後,若天氣情況良好,施工隊將開始東南角及西南角的人行道過道處安裝無障礙路緣斜坡, 預計於二月中旬前完畢,並在農曆新年街會及大巡遊後完成最後的水泥鋪面工序。
薩特街及士德頓街路口:預計一月前完成電力工程。將在安全島、西北角、西南角以及東南角安裝無障礙路緣斜坡。工程預計於四月底完工。
 
10/4/2024: 
Clay & Grant Intersection:  All structural construction has paused and is pending a redesign. No further update at this time.
Sutter & Stockton Intersection: Project is currently waiting for PGE to perform utility relocation before PW project can proceed with construction.
 
截至2024年10月4日:
企李街都板街交叉路口: 由於施工圖需進行修改,現場所有施工暫停。目前無更多信息。
薩特街士德頓街交叉路口:等待太平洋煤電公司將街燈移至不受工程影響位置。一旦完成,工務局即可開始施工。
 
 
Pavement and Sewer Renovation
Location
The Clay Street and Grant Avenue intersection and the Sutter Street and Stockton Street intersection
Districts
District 3
Start
Summer, 2024
Completion
Fall, 2025
Budget
$1.4 Million
Project Manager
Anastasia Haddad
Project Team

San Francisco Public Works

San Francisco Municipal Transportation Agency

San Francisco Public Utilities Commission

Contact
Anastastia Haddad