Main menu

  • Photo of intersection of Mission and Persia Streets
  • Mission Geneva Phase 1 Rendering
  • Mission Geneva Phase 2 Rendering
  • Mission Geneva Phase 3 Rendering
  • Mission Geneva Phase 4 Rendering

Mission Street and Geneva Avenue Infrastructure Improvement Project

Project Update (June 2024):

The contractor continues working on any punch list items in Segment I (Geneva Ave., from Mission St. to Prague St.). That work is expected to wrap up in the coming weeks.
 
Crews are scheduled to grind and pave (G&P) Segment II (Mission St., from Geneva Ave. to Russia Ave.) starting next week. That work is anticipated to take 2 days to complete on each block. The G&P phase will be followed by any punch list work identified in Segment II. The sequencing for G&P in Segment II is as follows:
 
Monday 7/22/24
Mission Street (Russia Avenue to Italy Avenue) - Grind
 
Tuesday 7/23/24
Mission Street (Russia Avenue to France Street) - Repave
 
Wednesday 7/24/24
Mission Street (France Street to Italy Avenue) - Repave
 
Thursday 7/25/24
Mission Street (Italy Avenue to Geneva Avenue) - Grind
 
Friday 7/26/24
Mission Street (Italy Avenue to Geneva Avenue - Repave
 
Monday 7/29/24
Mission Street (Geneva Avenue to Rolph Street) - Grind & Pave
 
Day 1
During the grinding phase (removal of existing asphalt from the roadway), access to enter and exit driveways will be maintained, however long delays should be expected if crews are working on the lane closest to your driveway. Please allow extra travel time.
 
Day 2
During the paving phase, driveway access may be delayed while crews work on the lane closest to your driveway. The contractor will apply a tack coat (liquid asphalt) to the roadway in advance of the hot asphalt. The tack coat promotes bonding between the concrete street base and the hot asphalt. During application of the tack coat and new asphalt, driveway access will not be possible until the asphalt cools-down. We apologize for the inconvenience.

 
What's Next?
Once we've completed work in Segment I and Segment II, we plan to have the contractor mobilize to Segment IV. We were planning to continue working sequentially into Segment III however due to contractor availability, we now plan to have them start in Segment IV. The specialized contractor is scheduled to start roadway deck repairs on the I-280 overpass bridge. The work in Segment IV is anticipated to take approximately 5 months to complete.

 

Project Description:
San Francisco Public Works, the San Francisco Municipal Transportation Agency (SFMTA), and the San Francisco Public Utilities are partnering to bring safety improvements and infrastructure upgrades to the Excelsior and Outer Mission neighborhoods. The Mission Street and Geneva Avenue Infrastructure Improvement Project includes approximately forty sidewalk bulb-outs, upgraded traffic signals at twenty locations, sewer main replacement at ten locations, concrete street base replacement work and street repaving throughout the project area. The project limits are:

  • Geneva Avenue: Prague Street to Mission Street
  • Mission Street: Geneva Avenue to Highway 280 Overpass (Trumbull Street)
     

Mission Street and Geneva Avenue are part of San Francisco's Vision Zero High Injury Network - the 13% of city streets where 75% of the severe and fatal collisions occur. The City and County of San Francisco adopted Vision Zero as a policy in 2014, committing to build better and safer streets, educate the public on traffic safety, enforce traffic laws, and adopt policy changes that save lives. The goal is to create a culture that prioritizes traffic safety and to ensure that mistakes on our roadways don’t result in serious injuries or death. The result of this collaborative, citywide effort will be safer, more livable streets as we work to eliminate traffic fatalities.

Once construction starts, we'll be sending regular e-updates to inform neighbors about the current and upcoming scopes of work, possible impacts, weekend work, completed project milestones, etc. Neighbors interested in receiving e-updates could SIGN-UP HERE.

For additional information on this project, please visit https://www.sfmta.com/projects/mission-geneva-safety-project
 

Project Sequencing & Duration

The overall project duration is anticipated to be approximately 3 years. However, in order to minimize any impacts associated with construction, this project will be completed in segments. A completion timeline has been placed on each segment to minimize the time it is under construction. There will be an overlap in segments as work is completed in one segment and starts on the next one. The segments are as follows:
 
Segment I 
Geneva Avenue (Mission Street to Prague Street) 
(Approximately 11.5 months / November 2022 – November 2023)
 
Segment II 
Mission Street (Geneva Avenue to Russia Avenue)
(Approximately 10 months / September 2023 – June 2024)
*** Note: Upon competion of Segment II, the contractor will mobilize to Segment IV ***
 
Segment III
Mission Street (Russia Avenue to Theresa Street) 
(Approximately 11 months / January 2025 – November 2025)
 
Segment IV
Mission Street (Theresa Street to Trumbull Street/ Hwy 280 overpass)
(Approximately 6 months / August 2024 – January 2025)
 
 

Pavement and Sewer Renovation
Location
Mission Street between Geneva Avenue and Trumbull Street, Geneva Avenue between Mission Street and Prague Street
District
Start Fall, 2022
Completion Spring, 2026
Release Date
Friday, August 20, 2021
Budget
$20,000,000
Client
San Francisco Municipal Transportation Agency (SFMTA), San Francisco Public Utilities Commission (SFPUC)
Project Manager
Paul Barradas: (628) 271-2580
Project Team

- S.F. Public Works
- S.F. Municipal Transportation Agency (SFMTA)
- S.F. Public Utilities Commission (SFPUC)
- Bauman Landscape and Construction, Inc.
  (415) 447-4800 Office
  (415) 985-5641 After-Hours 

Contact
Alex Murillo: (628) 271-2244
Download Project Files
Full Project Rendering