San Francisco Public Works has contracted with Esquivel Grading and Paving, Inc. to re-pave the roadway, build new curb ramps, and perform sewer work at various locations in San Francisco as part of the Hunters Point, Central Waterfront and Potrero Hill Area Pavement Renovation and Sewer Replacement Project.
All of the blocks listed below have been identified as prime candidates for repaving and street base repair due to their current conditions and amount of wear. Reconstructing these streets now will prevent possible damage and deterioration that may pose future safety risks.
We will also be performing some small-scale sewer work on a handful of these blocks. Most sewer work on this project will be to improve drainage in low laying areas through the construction of new sewer culverts. Work hours will vary by location, however, typical working hours are 8 a.m. to 5 p.m. Monday through Friday. Weekend work is allowed but has not been scheduled at this time.
To receive regular construction updates via email, you can sign up for our mailing list here.
Street resurfacing work will be taking place on the following blocks. Only those in bold will be receiving sewer work as well:
Wisconsin Street from 16th to 17th
De Haro Street from 15th to 16th
Rhode Island Street from Mariposa to 18th
Rhode Island Street from 23rd to 24th - In Progress
25th Street from Utah to Vermont - In Progress
Newcomb Ave from Newhall to 3rd
Mendell Street from Cargo to Newhall
Hunters Point Boulevard from Evans to Hawes - Sewer work on Hawes Street is in progress
Earl Street from Kirkwood to Jerrold - Complete
Kirkwood Avenue from Earl to La Salle - Complete
Construction Updates
10/21/24: UPDATE: Sewer work at the intersection of Griffith Street and Innes Avenue has been postoned. It will now bewgin on Thursday, October 30.
10/16/24: Starting next Monday, October 21st, we will be performing sewer work at the intersection of Griffith Street and Innes Avenue.
Specifically, we will be constructing two new sewer culverts at this intersection. These will connect the sewer system to the new storm drains we will be installing at the southwest and southeast corners of this intersection. Once these culverts are built, we will be constructing 6 new, ADA-compliant curb ramps at this intersection - 2 at each of the northeast, southeast and southwest corners. In total, we expect this work to take about 4 to 5 weeks to complete.
Once all sewer and curb ramp work is complete, we will rebuild small portions of the concrete street base near the newly built curb ramps and sewer infrastructure. After this work is complete, we will be performing additional roadway reconstruction on Innes Avenue from Ingalls Street to Arelous Walker Drive. Additional notice will be given prior to this work.
9/17/24: Street base reconstruction and re-paving on Earl Street, Kirkwood Avenue and Northridge Road has been postponed. It will now start on Monday, September 30th.
9/11/24: Street base reconstruction and re-paving on Earl Street, Kirkwood Avenue and Northridge Road starting on Monday, September 16th.
Starting next Monday, September 16th, our crews will begin repairing damaged portions of the concrete street base on the following streets:
We expect this work to take roughly 7 to 10 working days to complete in total. After all street base reconstruction work is complete, all three blocks will be fully re-paved. Additional notice will be provided one re-paving work is scheduled.
8/23/24: Sewer culvert construction at the intersection of Minnesota Street and 26th Street is starting on Monday, August 26th.
In total, we expect this work to take 1 week to complete. After sewer work is complete, we will be fully re-constructing the concrete street base and asphalt pavement on Minnesota Street between 25th Street and Cesar Chavez Street. Additional notice will be given prior to this work.
8/5/24: Sewer Main Replacement on Hawes Street between Hunters Point Boulevard and Innes Avenue is starting on Monday, August 12th.
7/26/24: Sewer Work at the Intersection of Rhode Island Street and 23rd Street is starting on Monday, August 5th.
Starting Monday, August 5th, our contractor will be constructing a new sewer culvert at the 23rd Street and Rhode Island Street instersection. This sewer culvert will connect the existing sewer to a new catch basin, which we will be installing at the intersection afterward. Once this sewer work is complete, we will be constructing four new, ADA-compliant curb ramps at this intersection - two at the northeast corner and two at the southeast corner.
Then, we will be reconstructing a portion of the concrete street base on Rhode Island Street between 23rd Street and 24th Street. Once this work is complete, we will fully re-pave the block. Additional notice will be given prior to re-paving work.
7/11/24: Sewer Main Replacement on 25th Street between Utah Street and Vermont Street is starting on Monday, July 29th.
Starting Monday, July 29th, our contractor will be replacing a portion of the sewer main on 25th Street between Utah Street and Vermont Street. Specifically, they will be repairing a section of the sewer main in front of 2501, 2516, 2518, 2527 and 2529 25th Street, roughly in the middle of the block. Once the sewer main is replaced, we will then inspect the block's sewer laterals and replace them on an as-needed basis. Sewer laterals are what connect household plumbing to the sewer main. In total, we expect sewer work to take 2 weeks to complete on this block. Once all sewer work is complete on this block, it will be fully re-paved. Additional notice will be given prior to re-paving work.
San Francisco Public Works
Esquivel Grading and Paving, Inc.