Various Locations Pavement Renovation and Sewer Replacement Project No. 63

Project Description

San Francisco Public Works has contracted with Ronan Construction Inc. to install new sewer utilities and renovate the roadway at various locations in San Francisco as part of the Various Locations Pavement Renovation and Sewer Replacement Project No. 63 (VL63). We will be performing this work in the Marina, Cow Hollow, Russian Hill and Cathedral Hill neighborhoods. 

We have inspected the sewer facilities of all the blocks listed below, and will be replacing those that we found to be cracked and/or broken.  Replacing these pipes now will prevent possible collapse of the sewer mains and pavement in the future. Sewer service will not be interrupted during the construction.  Pavement Renovation and Sewer replacement work will occur between February 2024 and September 2024.

This project will include sewer main replacement, curb ramp installation, street base repairs and repaving. Work hours will vary by location, however, typical working hours are 8 a.m. to 5 p.m. Monday through Friday. Weekend work is allowed but has not been scheduled at this time.

Street resurfacing work will be taking place on the following blocks. Only those in bold will be receiving sewer work as well:

Scott Street from Lombard Street to Chestnut Street - Complete

Webster Street from Lombard Street to Chestnut Street - Complete

Beach Street from Pierce Street to Cervantes Street - Complete

Sharp Place from Union Street to End - Complete

Bay Street from Laguna Street to Octavia Street - Complete

Bay Street from Gough Street to Franklin Street - Complete

Larkin Street from Union Street to Vallejo Street - Complete

Leavenworth Street from Clay Street to California Street - Complete

Vallejo Street from Hyde Street to Jones Street - Complete

Jones Street from Broadway to Vallejo Street - Complete

Pacific Avenue form Polk Street to McCormick/Morrell Street - Complete

Pacific Avenue from Hyde Street to Leavenworth Street - Complete

Myrtle Street from Franklin Street to Van Ness Avenue - Complete

Peter Yorke Way from Geary Boulevard to Post Street - Complete

McCormick Street from Pacific Avenue to End - Complete

 

Project Updates

10/1/24: On Thursday, October 3rd and Friday, October 4th, we will be re-paving Leavenworth Street between California Street and Clay Street. The first step of this work is to grind away the existing asphalt roadway surface. This will take place on all blocks on Octgober 3rd. The following day, we will re-apply 2 new inches of asphalt to the roadway of these blocks. This work should is expected to take two days to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
 
9/4/24: Starting on Monday, September 9th, we will be performing sewer, street base and paving work on Leavenworth Street between California Street and Clay Street. The first step of this work is to repair some damaged sewer laterals at the southeast corner of both the Leavenworth and Clay and Leavenworth and Sacramento Street intersections. Once this is complete, we will be constructing new concrete bus pads at the same two corners. The final step of this work will be to re-pave all of Leavenworth between California and Clay streets. In total, we expect this work to take 4 weeks to complete.
 
8/30/24: On Thursday, September 5th, we will be re-paving McCormick Street between Pacific Avenue and the end of the roadway. The first step of this work is to grind away the existing asphalt roadway surface. Then, we will re-apply 2 new inches of asphalt to the roadway. This work should is expected to take one day to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
 
8/5/24: On Tuesday, August 13th and Wednesday, August 14th, we will be re-paving Beach Street between Pierce Street and Cervantes Boulevard/Mallorca Way as well as Webster Street between Chestnut Street and Lombard Street. The first step of this work is to grind away the existing asphalt roadway surface. This will take place on both blocks on August 13th. The following day, we will re-apply 2 new inches of asphalt to the roadway of both blocks. This work should is expected to take two days to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
 
6/12/24: On Monday, June 17th and Tuesday, June 18th, we will be re-paving Larkin Street between, Vallejo Street and Union Street.  The first step of this work is to grind away the existing asphalt roadway surface. Then, we will re-apply 2 new inches of asphalt to the roadway. This work should is expected to take one day to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
 
5/30/24: On Monday, June 10th through Friday, June 14th, we will be re-paving Vallejo Street, Jones Street and Pacific Avenue. The specific order of this work is as follows:
 
Monday, June 10th: grind existing asphalt from the roadway on Vallejo Street from Hyde Street to Jones Street, as well as on Jones Street from Vallejo Street to Broadway
Tuesday, June 11th: re-pave Vallejo Street from Hyde Street to Jones Street
Wednesday, June 12th: grind existing asphalt from the roadway on Pacific Avenue from Leavenworth Street to Polk Street
Thursday, June 13th: re-pave Jones Street from Vallejo Street to Broadway as well as Pacific Avenue from Leavenworth Street to Hyde Street
Friday, June 14th: re-pave Pacific Avenue from Hyde Street to Polk Street.
 
This work should is expected to take one week in total to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
 
5/14/24: PLANNED CURB RAMP CONSTRUCTION ON WEBSTER STREET HAS BEEN POSTPONED. Instead, we will be starting curb ramp construction work on Larkin Street next Monday, May 20th.
 
First, we will begin constructing 2 new, ADA-compliant curb ramps at the intersection of Larkin Street and Rockland Street. Then, we will be constructing 6 new, ADA_compliant curb ramps at the NE, NW and SW corners of the Larkin Street and Vallejo Street Interseciton. Finally, we will be constructing 6 new, ADA-complaint curb ramps at the NE, NW and SW corners of the Larkin Street and Green Street intersection. 
 
We expect this work to take three to four weeks to complete in total barring any unforeseen circumstances or inclement weather. There will be some restrictions to on-street parking on these blocks of Larkin Street while this work is taking place, but there are no planned street or lane closures. A few weeks after this work is complete, our crews will return to re-pave LarkinStreet from Union Street to Vallejo Street.
 
4/24/24: On Monday, April 29th through Wednesday, May 1st, we will be re-paving Scott Street between Chestnut Street and Lombard Street. The first step of this work is to repair a small patch of concrete street base in the center of the block that is currently damaged We will perform this work on Monday the 29th and Tuesday the 30th. Then, our crews will grind away the existing asphalt roadway surface and re-apply 2 new inches of asphalt to the roadway. We will be performing this work on Wednesday the 1st. This work should is expected to take three days to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
 
4/12/24: Starting April 16th, we will be replacing sewer laterals in two locations - on Pacific Avenue at the Polk Street intersection and on Leavenworth Street at the Clay Street intersection. We expect this work to take four days to complete in total at both locations. Once this work is complete, we will be constructing new, 10-inch thick concrete bus pads over the area that we've replaced sewer laterals. This bus pad construction work is scheduled to begin on April 25th. Once the concrete for these bus pads is poured, it will need a few days to properly dry and cure, and a portion of the street will need to be blocked off to all traffic to allow this to happen. Specifically, the bus pads will be constructed at the southeast corner of Leavenworth and Clay (in front of 1248 - 1258 Leavenworth) and at the northeast and southeast corners of Pacific and Polk (in front of 1572 Pacific and 1591 Pacific). 
 
 
4/4/24: Starting April 8th, we will be replacing the sewer main on Jones Street between Lombard Street and Vallejo Street. Once we install the sewer main on this block, we will then replace any damaged sewer laterals, which are the smaller pipes that run perpendicular to the curb and connect the sewer main with household plumbing systems. We expect this work to take about 3 to 4 weeks to complete, barring any unforeseen circumstances. After sewer work on this block is complete, we will then begin sewer main replacement on Vallejo Street between Jones Street and Hyde Street. You will receive additional notice about this work in the mail roughly 10-15 days before it is schedule to begin.
 
3/22/24: On Monday, March 25th, we will be re-paving Peter Yorke Way between Geary Boulevard and Post Street. The first step of this work is to grind away the existing asphalt roadway surface. Then, we will re-apply 2 new inches of asphalt to the roadway. This work should is expected to take one day to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
 
On Tuesday, March 26th and Wednesday, March 27th, we will be re-paving Bay Street between Franklin Street and Laguna Street. The first step of this work is to grind away the existing asphalt roadway surface. We will be performing this work on Tuesday the 26th. Then, we will re-apply 2 new inches of asphalt to the roadway. We will be performing this work on Wednesday the 27th. This work should is expected to take two days to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
 
From March 26th through the 28th, we will be constructing a new sewer manhole at the intersection of Pacific Avenue and McCormick Street. In order to perform this work, we will need to close McCormick Street to all vehicle traffic from 8am to 5pm on Tuesday, March 26th, Wednesday March 27th and Thursday, March 28th.This means that access to all garages and driveways on McCormick Street will be restricted during these times.
 
If you need to access your vehicle during these periods, please make other parking and vehicle access arrangements. Roadway, driveway and garage access will be restored each evening by 5pm.
 
We sincerely apologize for any inconvenience that this may cause, and assure you that we will be making these necessary sewer improvements in a quick and efficient way as possible.
 
A few weeks after we construct this new manhole, we will be coming back to build a new raised crosswalk across McCormick at the Pacific Avenue intersection. This may require similar temporary road closures. You will receive additional notice a few weeks prior to the start of this work.
 

 

Project Updates

Pavement and Sewer Renovation
STATUS In Progress
Location
Throughout the Marina, Cow Hollow, Russian Hill and Cathedral Hill Neighborhoods
Start Winter, 2024
Completion Fall, 2024
Budget
$2.7 Million
Project Manager
Ramon Kong
Project Team

San Francisco Public Works

Ronan Construction, Inc

Contact
Benjamin Peterson
Phone
(628)271-3057