Project Description

San Francisco Public Works is scheduled to complete infrastructure improvements on several blocks throughout the city as part of our Various Locations #67 project. This project may include curb ramp installation, concrete street base repairs, grinding (removal of existing asphalt) and repaving.

Construction will begin at the first location in July 2024 with completion expected at the last location in January 2025. San Francisco Public Works will manage the project during construction. The work hours may vary by location; however, the typical working hours are 7:30 AM to 5 PM, Monday through Friday. Weekend work is allowed but is not anticipated at this time.

Below is a list of the blocks scheduled to be repaved under this contract:

  • Lake Street (19th Avenue to 16th Avenue)
  • Lake Street (12th Avenue to 11th Avenue)
  • 14th Avenue (Lake Street to California Street)
  • 14th Avenue (Clement Street to Geary Blvd.)
  • 14th Avenue (Cabrillo Street to Fulton Street)
  • 10th Avenue (California Street to Lake Street)
  • Anza Street (Park Presidio Blvd. to Funston Avenue)
  • Anza Street (2nd Avenue to Arguello Blvd.)
  • Lyon Street (Geary Blvd. to O’Farrell Street)
  • Alpine Terrace (Duboce Avenue to 14th Street)
  • Duboce Avenue (Castro Street to Noe Street)
  • Henry Street (Castro Street to Noe Street)
  • Hattie Street (Corbett Street to Market Street)
Pavement and Sewer Renovation
STATUS In Progress
Location
Various locations throughout the Inner Richmond, Lower Pacific Heights, Corona Heights, and Duboce Triangle neighborhoods
Start Summer, 2024
Completion Winter, 2025
Budget
$3 million
Project Manager
Ramon Kong
Project Team

San Francisco Public Works

Esquivel Grading and Paving, Inc.

Contact
Alex Murillo
Phone
628-271-2244