February 17- March 2026 Construction Schedule

Esquivel Grading & Paving (EGP) and JDB crews will be active along Powell Street from Francisco to Filbert over the next 60 days. Work will progress block-by-block and at multiple intersections.

 

Powell Street/ (Francisco to Filbert)
 

Concrete Work

Corner ramp and concrete sidewalk work is slated to begin at the following intersections along Powell Street:

  • Powell & Chestnut (NE, NW, SE, SW corners)
  • Powell & Francisco (SW corner)
  • Powell & Lombard (SW corner)
  • Powell & Greenwich (NE and SE corners)  starting 3/1/26

 

Additional Improvements

  • Powell & Greenwich (NE): Concrete paving operations in progress starting 2/23/26.
  • Powell & Francisco: Bus pad installation underway starting 3/1/26

 

 

Sewer Work (SW) 

  • Installation of 10” VCP culvert and catch basins
  • Ongoing sewer work at intersections including:
    • Powell & Francisco
    • Powell & Chestnut
    • Powell & Lombard
    • Powell & Greenwich (NE/SE corners)

 

Roadway Improvements 

  • Base repairs
  • Grinding and paving operations
  • Work limits include:
    • Powell St (Francisco to Filbert)
    • Powell St (Filbert to Lombard)

 

 

Grant Avenue (Broadway Street to Pine Street)

This work consists of roadway pavement renovation, including roadway base repair, curb ramps and one-block of sewer-replacement.

 

Sewer work location: Pine St. – California St.

 

Curb ramp work locations:

  • Commercial St. & Grant Ave.
  • Vinton Ct. & Grant Ave.
  • Pine St. & Grant Ave. (southwest corner)

Roadway work locations:

  • Pine St. – California St. 
  • Sacramento St. – Broadway

 

Construction duration is two months 

starting March 9, 2026, through early May 2026.

 

Join us at our Community Meeting:

  • Tuesday, March 3, 1:30PM – 2:30PM
  • Willie “Woo” Wong Clubhouse

(830 Sacramento St., SF, CA 94108)

RSVP: https://forms.office.com/g/p2qPFmzqfm

 

 

 

🔧 What Is Grind & Pave?

Grind and pave is a multi-step process that includes:

  1. Grinding – Crews remove the top layer of existing asphalt using specialized equipment. This may result in a rough surface temporarily.

  2. Base & Concrete Work (select areas) – Concrete base repairs, sidewalk work, or related improvements may occur before paving.

  3. Paving – A new layer of asphalt is installed to create a smoother, safer roadway.

  4. Striping & Final Touches – Lane markings and final adjustments are completed following paving.


Work Hours

Monday through Friday: 7:00 AM – 5:00 PM

  • Work may begin as early as 7:00 AM

  • Traffic lane restrictions and tow-away enforcement begin at 8:00 AM

  • Weekend work is allowed; however, none is anticipated at this time

*Schedules may change due to weather or unforeseen conditions.


🚗 Traffic, Parking & Access

  • Temporary lane closures and traffic delays should be expected

  • Driveway access will be maintained, though brief delays may occur while crews work nearby

  • On paving days, vehicles may need to be temporarily relocated to allow asphalt placement and curing

  • Please observe posted “No Parking / Tow Away” signs on construction barricades for exact dates and times

  • Allow extra travel time during construction hours


🔊 Noise & Construction Activity

Residents may notice:

  • Construction noise from grinding and paving equipment

  • Increased truck traffic in the area

  • Dust and vibrations during grinding operations

These impacts are temporary and necessary to complete the work efficiently and safely.


Thank You for Your Patience

We appreciate your cooperation as we complete these important roadway improvements. This work will result in smoother streets, enhanced safety, and longer-lasting pavement for the community.

Thank you for your understanding during construction!

 

Status
In Progress
Start
Spring, 2025
Completion
Winter, 2026
Client
PUC
Project Manager
Paul Barradas
Project Team

Adalbert Cuellar-Franco, Resident Engineer

Contractor: Esquivel Grading and Paving

Carlos Siqueira / Project Manager

PO Box 24-107. San Francisco, CA 94124

Tel: (415) 468-5700   /   Urgent After-hours contact: (415) 354-4870

Email: carlos@esquivel-gp.com

Contact
Dadisi Najib, Public Affairs