13th Street Safety Improvement Project

Sign up to receive construction updates via email here
 
Project Update (August 27, 2026)
•    San Francisco Public Works continues work on the 13th Street Safety Improvement Project. 
•    The contractor completed curb ramps at the northwest corner of Mission/13th/Otis intersection 
•    The contractor completed medians at the western and eastern side of 13th St & Folsom St and the southeast median at 13th & South Van Ness Ave
•    Crews are finishing up curb ramp work at the US-101 On Ramp & South Van Ness & southeast corner of Mission/13th/Otis. 
•    Crews continue curb ramp and median work at the 13th & Folsom, 13th & South Van Ness, and the Mission/13th/Otis intersections.
•    The Contractor is working on the traffic signals at the 13th & Folsom, 13th St & South Van Ness and the Mission/13th/Otis intersections.
 

Project Description
The 13th Street Safety Project will enhance safety and comfort for everyone who travels along the 13th Street corridor between Folsom Street and Valencia Street. The project aims to reduce conflicts among people walking, biking, and driving by implementing a series of targeted transportation safety improvements.
 

Planned upgrades include:
 

  • Sidewalk extensions to increase pedestrian visibility and shorten crossing distances

  • Signal timing and hardware upgrades to better organize and manage traffic flow

  • Protected bike lanes to physically separate people biking from vehicle traffic

  • Parking and loading zone changes to make more efficient use of curb space


This project is part of San Francisco’s High-Injury Network—the 13% of city streets where 74% of severe and fatal traffic collisions occur. Between 2018 and 2022, there were 100 reported collisions resulting in injuries in the project area. Over one-third of those collisions involved pedestrians or bicyclists. The most common contributing factors were red light violations, high speeds, and unsafe left turns, making 13th Street one of the city’s most collision-prone corridors.
 

By improving infrastructure for all modes of travel, the project will enhance multimodal safety and provide critical connections in San Francisco’s bicycle network, with direct links to the Folsom Street, Valencia Street, and Division Street corridors.

 
 
 
 
 
Public Safety
Location
13th St. between Valencia St. and Isis St.
Districts
District 6
District 8
District 9
Start
Winter, 2025
Completion
Winter, 2027
Budget
$9 Million
Client
SFMTA
Project Manager
Lorina Louie - 628-271-2467
Project Team

• San Francisco Municipal Transportation Agency
• San Francisco Public Utilities Commission 
• Caltrans
• NTK Construction, Inc.
  (415) 643-1900 Main
  (415) 715-7598 After-Hours/Urgent

Contact
Alex Murillo