15th Avenue Pavement Renovation

Project Information 

Under direction of DPW, 15th Avenue in the Richmond District will be resurfaced with fresh asphalt.  This work will follow removal of the aging pavement; repairs to the concrete street base, sidewalks, curb & gutters; and installation of curb ramps at intersections between Fulton & California streets.

Project Update 

Construction Completed.

Project Location 

15th Avenue, from Fulton to California streets.

Project Duration 

85 Calendar Days

Project Team 

Department of Public Works

Contractor 

Esquivel Grading & Paving

Contact 

Bill Adams 

Office of Communications & Public Affairs 


415-437-7038