Project Update 7/16/12

Marina Boulevard     DPW contractor A. Ruiz Construction Inc. are grinding away the old asphalt, between Laguna and Buchanan in front of the Safeway. The roadway is open to thru traffic, however motorists should expect minor delays. This work will wrap up Wednesday with final paving. 

Columbus Street        Curb-ramp work began last week July 9th and sewer work at the Bay Street intersection will begin sometime this week July 16th.

Project Description 

This project includes curb-ramp replacement with new ADA ramps, sidewalk, curb and gutter, parking strip, bus-pad and  track removal.  

Additionally there will be some spot-sewer repairs on Lyon Street between Union Street and Lombard (3-blocks) and on Columbus between Bay Street and Chesnut Street (2-blocks). 

Lastly road-base repair and ashphalt paving will complete this project.  

 

Locations:

Marina Boulevard (Laguna Street to Scott Street) 5-blocks

Lyon Street (Green Street to Francisco Street) 6- blocks

Columbus Avenue (Powell Street to Beach Street) 7-blocks

Duration: 180-days 

Start Date: March 2012

End Date: December 2012

Working Hours: Monday through Friday 9:00 AM to 3:00 PM

Contact:

Dadisi Najib

DPW, Communications and Public Affairs

415-437-7018

dadisi.najib@sfdpw.org

 

Afterhours Emergency Contact 

A. Ruiz Construction 

415-559-2938 or 415-647-4010