Various Locations #77 Paving and Sewer Renovations
November 2026
Upcoming construction: October 26 – November 14, 2026
Construction crews with Esquivel Grading & Paving will continue work at several locations throughout San Francisco as part of the VL77 Pavement Renovation No. 77 and Sewer Replacement Project. Over the coming weeks, crews are scheduled to perform sewer repairs and replacements, roadway base repairs, pavement grinding and paving, and work on bus pads and speed cushions.
Work will take place in phases and may vary by location as crews coordinate with City agencies and utility providers.
Upcoming construction activities
| Location | Planned work | Tentative schedule |
| 18th Avenue, Ortega to Noriega streets | Sewer lateral replacement, followed by trench restoration and roadway repairs | Oct. 26–Nov. 14 |
| Warren Drive, Devonshire Way to Christopher Drive | Sewer lining, base repairs, grinding, paving and speed cushions | Oct. 26–Nov. 14 |
| Warren Drive and Blairwood Lane | Sewer replacement | Oct. 26–30 |
| Foerster Street | Manhole repairs | Week of Oct. 26 |
| Taraval Street | Manhole repairs | Week of Oct. 26 |
| Ulloa Street, West Portal Avenue to Claremont Boulevard | Sewer replacement | Beginning Oct. 26; duration not confirmed |
| 38th Avenue, Wawona to Vicente streets | Roadway grinding and paving | Nov. 9–13 |
| Foerster Avenue, Melrose to Teresita Boulevard | Base repairs, grinding and paving | Nov. 9–13 |
| Junipero Serra Boulevard, Holloway to Lyndhurst drives | Base repairs, grinding and paving | Nov. 9–13 |
| Sloat Boulevard, 19th Avenue to Cranleigh Drive | Roadway repairs and paving | Pending sewer/design coordination |
| Santa Ana Avenue, Ocean to St. Francis boulevards | Base repairs, grinding and paving | Nov. 5–6 |
| Ulloa Street, West Portal Avenue to Claremont Boulevard | Roadway repairs and paving | Dates not confirmed |
| Taraval Street, 12th Avenue to Claremont/Montalvo avenues | Roadway repairs and paving | Dates not confirmed |
| Laguna Honda Boulevard, Ulloa to Portola streets | Bus pad and roadway improvements | Dates not confirmed |
What to expect
Construction may require temporary work zones and could affect parking, vehicle travel, sidewalks, or access near active work areas. Impacts will vary depending on the type and location of work.
Please use caution when traveling near construction zones, follow posted signs and directions from crews, and allow additional time when traveling through affected areas.
Some activities are still awaiting approvals, utility coordination, or design revisions. These include certain traffic control plans, sewer work and roadway redesigns, as well as coordination with PG&E and SFPUC. As a result, portions of the schedule may change.
Schedule reminders
The contractor's three-week look-ahead schedule, dated October 23, 2026, is tentative and subject to change. Work dates may shift due to field conditions, weather, utility coordination, design approvals, or other construction requirements.
Project Overview
San Francisco Public Works has hired Esquivel Grading & Paving, Inc. to improve streets and underground infrastructure at various locations throughout San Francisco as part of the Various Locations Pavement Renovation No. 77 and Sewer Replacement Contract (No. 1000038062). The project will include a combination of pavement renovation, curb ramp construction, sewer replacement and/or lining, traffic control, and related improvements. Because the work varies by location, the specific scope, schedule, and construction activities will be updated for each location as the project progresses.
Locations
· Warren Dr. Devonshire Way – Oak Park Dr.
· 18th Ave. Ortega St. – Noriega St.
· 38th Ave. Wawona St. – Vicente St.
· Santa Clara Ave. Terrace Dr. – Portola Dr.
· Sloat Blvd. 19th Ave. – Crainleigh Dr.
· Santa Ana Ave. Darien Way St. – Francis Blvd.
· Junipero Serra Blvd. Holloway Ave. – Lyndhurst Dr.
· Foerster St. Melrose Ave. – Teresita Blvd.
· Foerster St. Judson Ave. – Staples Ave.
· Taraval St. 12th Ave Claremont Blvd/ Montalvo Ave.
· Laguna Honda Blvd. Ulloa St. – Portola Dr.
· Ulloa St. Claremont Blvd. – West Portal Ave.
Construction Schedule
Construction is anticipated from June 2026 through August 2027. Residents, businesses, and other affected parties will receive a follow-up notice approximately 10 days before construction begins in their area.
General work hours are Monday through Friday, 8:00 a.m. to 5:00 p.m. Work may begin as early as 7:00 a.m.; however, traffic lane restrictions and tow-away restrictions will not begin until 8:00 a.m. Weekend work is permitted and may be necessary, although none is currently anticipated at this time.
Construction schedules and durations are subject to change due to weather, site conditions, or other unforeseen circumstances.
What to Expect During Construction
Driveway access will be maintained whenever possible, although temporary delays may occur when crews are working directly in front of a building. Intersection and lane closures may also result in traffic delays, so please allow additional travel time during construction.
Please pay close attention to posted “No Parking/Tow Away” signs on construction barricades. Work hours and days may vary depending on the construction activity and location. No Parking/Tow Away signs will be posted at least 72 hours before work begins on a block.
Contractor:
Esquivel Grading & Paving, Inc.
Carlos Siqueira, Project Manager
PO Box 24-107
San Francisco, CA 94124
Tel: (415) 468-5700
24/7 Contact: (415) 354-4870
Email: carlos@esquivel-gp.com