• Folsom Streetscape Project / Soma Rendering
  • Folsom Streetscape Project Rendering image
  • Folsom Streetscape Map 11th to 7th
  • Folsom Streetscape Map 7th to 5th
  • Folsom Streetscape Map 5th to 2nd

Folsom Streetscape/SOMA

Sign Up for Construction Updates Here

 

Construction Updates

October 3, 2025

 

Here is what is happening on Folsom Street :

Upcoming Work: Flat Work between 7th Street and 6th Street
Construction crews will begin flat work along Folsom Street between 7th Street and 6th Street starting Monday, October 6. Work is scheduled to continue through Saturday, November 30.  

What to Expect

Please note: The first and second day of demolition will be noisy as crews remove the old concrete. After that, crews will build forms, install temporary plywood ramps for access and mark the area with orange barriers during the new sidewalk, curb and gutter pours.  This phase is expected to wrap up by late November (within 7-8 weeks).

 

Segment 3 -Folsom Street 2nd St. to 5th St.

3rd St. to 4th St.

  • No Activity due to Moscone Events

4th St. to 5th St.

  • No Activity due to Moscone Events

     

Segment 2 - Folsom Street 5th St. to 8th St.

5th St. to 6th St.

  •  Finishing up the sidewalk replacement on the southside of Folsom and should be completed 10/8/25.
  • Crews will remove and replace the southside parking strip.  This work will take approximately two-weeks with completion the week of 10/20/25.


6th St. to 7th St.
Sidewalk Work between 7th Street and 6th Street
Construction crews will begin sidewalk replacement along Folsom Street between 7th Street and 6th Street starting Monday, October 6. Work is scheduled to continue through Saturday, November 30.

The sequence of work will proceed as follows:

  1. North Side Sidewalks – demolition and replacement of sidewalks.  Approximately 2 weeks through 10/17/25
  2. North Side Street Base – preparation and installation of new roadway base.  Approximately 1-2 weeks through end of October.
  3. South Side Corners & Sidewalks – improvements to pedestrian corners and sidewalks.  Late October.
  4. South Side Islands – construction of new median/island features.  Approximately 11/3/25
  5. South Side Street Base – roadway base work on the south side. Mid- November. 

 

7th St. to 8th St 

  •     


     

Segment 1 - Folsom Street 8th St. to 11th St.

 

8th St. to 9th St.

  • No Activity 

9th St. to 11th St. 

  • No Activity

     

For questions or coordination contact Dadisi Najib, SF Public Works


Project Description and Scope of Work:

SF Public Works has hired Mitchell Engineering to perform vital infrastructure improvements along Folsom Street between 2nd Street to 11th Street.  The Folsom Streetscape Project which began in May of 2024 has an overall duration of 2-years, 7-months (950-days).

The project scope of work consists of sewer and water replacement, curb ramp reconstruction, pavement renovation landscaping, street lighting, and traffic signals.  

We are aware of the inconvenience caused by construction and apologize in advance.  We will do everything possible to minimize the impact of our activities on your neighborhood.  If you have concerns (scheduled deliveries, construction questions, accessibility needs, and access) please contact Public Affairs, Dadisi Najib. 

Your cooperation will help this project be a success for your neighborhood and the City of San Francisco.  Thank you in advance for your understanding and cooperation.


For more information please visit:

https://www.sfmta.com/projects/folsom-howard-streetscape-project

https://www.sfmta.com/projects/folsom-street-implementation

 

 

 

 

Public Safety
Streetscapes
Status
In Progress
Location
Folsom Street (2nd St. to 11th St.)
Districts
District 6
Start
Spring, 2024
Completion
Fall, 2026
Budget
45M
Client
SFMTA
Project Manager
Carol Huang
Project Team

Contractor - Mitchell Engineering

Contact
Ms. Dadisi Najib