Main menu

  • Folsom Streetscape Project / Soma Rendering
  • Folsom Streetscape Project Rendering image
  • Folsom Streetscape Map 11th to 7th
  • Folsom Streetscape Map 7th to 5th
  • Folsom Streetscape Map 5th to 2nd

Folsom Streetscape/SOMA

Sign Up for Construction Updates Here

Construction Update June 2024

Week of June 24th through July 30th, 2024 

Construction crews continue working this week on Folsom Street between 11th and 8th Street.  Crews are rebuilding the culverts and catch-basins as well as potholing in preparation for side-sewer lateral work.  This work will continue for the next couple of weeks.   

We have encountered an unexpected conflict in this segment between 8th and 11th Street resulting in some modifications to our work sequencing.  Our intended schedule had crews working eastbound from 11th Street, we now need to pivot and start mobilizing earlier than anticipated in the segments located between 2nd-8th Streets to keep the project moving forward. We have dispatched a small crew to start potholing the roadway on Folsom Street in the segments from 2nd St. to 8th St.  Potholing allows us to verify the pre-existing utilities underground before we start digging.  This scope takes about 1-week per block to complete and should have minimal impacts.   Should our underground investigation prove successful and there are no conflicts we will proceed with the replacement of the side-sewer lateral lines to properties (2-weeks maximum per block).

Following this work will be the main-line sewer rehabilitation which will be a cast in-place sewer-lining process 2nd to 3rd and 4th -5th.  This means you will not see an open trench as the work occurs underground with small crews at the surface manholes.  This work occurs around the clock (24-7) and will take approximately for 3-days to complete per block.

The sewer main replacement between 3rd and 4th Street will be an open trench (600-feet) and will take approximately 1-2-weeks to complete

 

Segment 3 -Folsom Street 2nd St. to 5th St.

  • Mobilization, layout and sawcut the roadway in preparation for catch-basin and culvert installation through 7/30/24

 

Segment 2 - Folsom Street 5th St. to 8th St.

*no work scheduled at this time

 

Segment 1 - Folsom Street 8th St. to 11th St.

  • Sewer work continues through 7/20/24
  • Demolition/Removal of Bus Island 6/24-6/26-24
  • Electrical Conduit, excavationfor pole foundations scheduled 7/15/24 -10/4/24

 

For questions or coordination contact Dadisi Najib, SF Public Works

Project Description and Scope of Work:

SF Public Works has hired Mitchell Engineering to perform vital infrastructure improvements along Folsom Street between 2nd Street to 11th Street.  The Folsom Streetscape Project beginning in May of 2024 has an overall duration of 2-years, 7-months (950-days) and is divided into three (3)-segments to help minimize impacts along the entire corridor. 

The project scope of work consists of sewer and water replacement, curb ramp reconstruction, pavement renovation landscaping, street lighting, and traffic signals.  Starting in June 2024, crews will prioritize working in the segment of Folsom Street from 11th St to 8th.

We are aware of the inconvenience caused by construction and apologize in advance. We will do everything possible to minimize the impact of our activities on your neighborhood. If you have concerns (scheduled deliveries, construction questions, accessibility needs, and access) please contact Public Affairs, Dadisi Najib. We will do everything possible to find a mutually agreeable solution.

Your cooperation will help this project be a success for your neighborhood and the City of San Francisco.  Thank you in advance for your understanding and cooperation.

For more information please visit:

https://www.sfmta.com/projects/folsom-howard-streetscape-project

https://www.sfmta.com/projects/folsom-street-implementation

 

 

 

 

Public Safety
Streetscapes
STATUS In Progress
Location
Folsom Street (2nd St. to 11th St.)
District
Start Spring, 2024
Completion Date October 31, 2026
Completion Fall, 2026
Release Date
Wednesday, January 31, 2024
Budget
45M
Client
SFMTA
Project Manager
Carol Huang
Project Team

Contractor - Mitchell Engineering

Contact
Ms. Dadisi Najib
Phone
628-271-2245
Download Project Files