December 10, 2024: Public Works has awarded the contract for Phase 1 of the Transbay Block 3 Project to NTK Construction. Last week, the Public Works project team held a pre-construction planning meeting with NTK Construction as well as a number of its sub-contractors. On January 20, 2025, Public Works will officially give NTK Construction Notice to Proceed (NTP) for this project. This designation officially kicks off the pre-construction period, in which the project schedule will be finalized, administrative documents will be submitted, and construction equipment and materials will be procured. Full time on site construction is expected to begin in early Spring 2025. The anticipated on-site construction start date will be posted once Public Works has an approved baseline schedule from the contractor.
Block 3 Park and adjacent Clementina and Tehama alleyways are central features of the Transbay Redevelopment Project Area, which was adopted in 2005 and includes 40 acres of high-density transit-oriented development, including housing, office space and retail in the East Cut, a new neighborhood just south of San Francisco's downtown and financial districts.
Block 3 Park was first conceptualized in the Transbay Redevelopment Plan and its accompanying documents, and later in the Transbay Project Area Streetscape and Open Space Concept Plan, dated Nov. 21, 2006. Select elements of the Concept Plan have been further refined in the Transit Center District Plan, authored in 2012. The Concept Plan included new public spaces, new alleyways, improvements to existing streets, widened sidewalks, street trees, lights, seating areas and other elements to enhance and complete the vision for the Transbay Redevelopment Project Area.
The project has been divided into two phases: Phase I - Streetscape Infrastructure, and Phase II - Block 3 Park and the Tehama Street Extension. Phase I - Streetscape Infrastructure scope of work includes new Clementina right-of-way, signalized crossing, sidewalk widening of Main and Beale Streets, and Main Street waterline relocation. Phase II – Block 3 Park will be a new 1-acre park that will be owned and maintained by the Recreation and Park Department with activations in partnership with East Cut Community Benefit District. Phases II is currently on hold for a minimum of two years, allowing The Crossing at East Cut interim activation on Transbay Blocks 3 and 4 to continue while the Office of Community Investment and Infrastructure (OCII, the Project sponsor) focuses on expedited delivery of the nearby Under Ramp Park Project (URP).
100% Schematic Design approved by:
Civic Design Review approval from the Arts Commission
SF PUC Stormwater Control Plan Preliminary review and approval (3/24/2023)
Community Meetings to review Park Design
Hosted by Public Works, Recreation and Park Department, Office of Community Investment and Infrastructure and East Cut Community Business District (ECCBD)
Community Meeting 4 – (04/29/2021)
Presentation of community-selected park program design alternative, the “Clearing” (online meeting with 51 attendees)
Community Meeting 3 – (11/18/2020)
Design Refinements and alternatives shared for public input (online meeting with 67 attendees)
Community Meeting 2 – (9/9/2020)
Initial Design Ideas shared with the public for input (online meeting with 77 attendees)
Community Meeting 1 – (3/4/20)
Information Gathering from the public (in-person meeting with 50 attendees)
Community Surveys conducted for community feedback: 4 total
Park Naming Community Meeting Process
Check out The East Cut Block 3 Park Naming Site and Watch the Zoom Meeting
Artist Selection Process
San Francisco Arts Commission Civic Design Review Board Process
Public meetings at SF Art Commisison were held to review and approve the project design:
Office of Community Investment and Infrastructure (OCII) Citizen Advisory Committee Public Meeting and presentation - 2/10/2022
Recreation and Park Department Public Meetings and presentations
San Francisco Public Works
SF Recreation and Park Department
San Francisco Municipal Transportation Agency
East Cut CBD (Future Park Programming Partner)