Hallidie Plaza Accessibility Improvements

The Hallidie Plaza Accessibility Improvement Project, at the north corner of Market Street and Cyril Magnin Street, will focus on accessibility improvements including the removal of the existing elevator as well as the construction of ramps both from street level to plaza level and from plaza level to the Powell Street BART/Muni Station.

 


Project Timeline

Planning: Summer 2025 - Fall 2025

Design: Fall 2025 - Winter 2026

Construction: Summer 2027 - Winter 2027

 

 

On July, 23 2025, the project team will be holding a community meeting and information session about this project. In advance of this meeting, you can ask any questions you might have about this project by clicking the link below. We will answer as many of your questions as possible during the event, and will answer all others directly via email.

 

Do you have a question for the project team?

 

Meeting Info:

  • Date: Wednesday, July 23, 2025
  • Time: 2:00PM - 4:00PM
  • Location: San Francisco Public Works Conference Room: 49 South Van Ness Avenue Room 0194, San Francisco, California
  • Zoom Login Info

 

Location
Hallidie Plaza, near the Market Street & 5th Street intersection
Districts
District 3
Start
Summer, 2027
Completion
Winter, 2027
Budget
$6,500,000
Project Manager
Anastastia Haddad & Christine Hunt
Project Team
  • San Francisco Public Works
  • San Francisco Mayor’s Office on Disability and Accessibility
  • San Francisco Real Estate Division
  • BART
Contact
Anastasia Haddad, anastasia.haddad@sfdpw.org, Christine Hunt, christine.hunt@sfdpw.org