Western Addition Traffic Signals Project

Project Description

San Francisco Public Works partnered with SFMTA to upgrade traffic signal infrastructure at 16 intersections in the Western Addition Neighborhood. The scope of work included wiring, Pedestrian Countdown Signals (PCS), Accessible Pedestrian Signals (APS) pushbuttons, vehicular signal heads, poles and mast-arms, and signal controllers. Additionally, curb ramp work, sidewalk work, curb and gutter work, median work, and local base repair and paving work is included in this contract.
 

Various Locations Pavement Renovation and Sewer Replacement No. 55

Project Update January 2025

  • R&S Construction will pour the sidewalk at Cesar Chavez St & Sanchez St on Monday January 13th, completing all work at this intersection. 
  • We are in our punch-list phase of this project.  By the end of this month there will not be any major construction on this project. 

     

Better Market Street

A renewed Market Street will anchor multiple downtown neighborhoods and link public open spaces. It will also connect the city’s Civic Center with cultural, social, convention, tourism, and retail destinations, as well as the Salesforce Transit Center, the regional transit hub. The vision is to make Market Street a place where people will want to stop and spend time, meet friends, people-watch while sitting in a café, or just stroll and take in the urban scene.