West Portal Avenue and Quintara Street Water Main, Sewer and Paving Project
The project will improve the infrastructure, making the area safer and more attractive for residents, businesses and visitors on this commercial corridor and the surrounding area.
 
This work will be performed in several phases over a 16-month duration (498-days). The project requires coordinating work with our partner agencies. Work to be performed includes:
- water main installation on West Portal Ave.
- sewer main work on West Portal Ave between 14th Ave and 15th Ave and at the intersection of West Portal Ave and Ulloa St
- bulb-out installations on West Portal Ave at Vicente St.
- new curb ramps along the project limits
- paving two parking lots within the project limits
- repaving along muni tracks
- roadway resurfacing on West Portal Ave
Pavement and Sewer Renovation
                              Transportation Projects
               Status
        
          Completed
        
      Location
        
          West Portal Ave. from 15th Avenue to Ulloa Avenue and Quintara Street  from 14th Ave to 10th Ave
        
      Districts
        District 8
                       Project Team
        ConQuest
City Planning 
District 7 Supervisor, Norman Yee
Neighborhood Merchants and Residents
Office of Economic and Workforce Development
Public Utilities Commission
Public Works
Municipal Transportation Agency
Contact
        
          Dadisi Najib
        