Various Locations Pavement Renovation and Sewer Replacement Project No. 63
Project Description
San Francisco Public Works has contracted with Ronan Construction Inc. to install new sewer utilities and renovate the roadway at various locations in San Francisco as part of the Various Locations Pavement Renovation and Sewer Replacement Project No. 63 (VL63). We will be performing this work in the Marina, Cow Hollow, Russian Hill and Cathedral Hill neighborhoods.
We have inspected the sewer facilities of all the blocks listed below, and will be replacing those that we found to be cracked and/or broken. Replacing these pipes now will prevent possible collapse of the sewer mains and pavement in the future. Sewer service will not be interrupted during the construction. Pavement Renovation and Sewer replacement work will occur between February 2024 and September 2024.
This project will include sewer main replacement, curb ramp installation, street base repairs and repaving. Work hours will vary by location, however, typical working hours are 8 a.m. to 5 p.m. Monday through Friday. Weekend work is allowed but has not been scheduled at this time.
Street resurfacing work will be taking place on the following blocks. Only those in bold will be receiving sewer work as well:
- Scott Street from Lombard Street to Chestnut Street - Complete
- Webster Street from Lombard Street to Chestnut Street - Complete
- Beach Street from Pierce Street to Cervantes Street - Complete
- Sharp Place from Union Street to End - Complete
- Bay Street from Laguna Street to Octavia Street - Complete
- Bay Street from Gough Street to Franklin Street - Complete
- Larkin Street from Union Street to Vallejo Street - Complete
- Leavenworth Street from Clay Street to California Street - Complete
- Vallejo Street from Hyde Street to Jones Street - Complete
- Jones Street from Broadway to Vallejo Street - Complete
- Pacific Avenue form Polk Street to McCormick/Morrell Street - Complete
- Pacific Avenue from Hyde Street to Leavenworth Street - Complete
- Myrtle Street from Franklin Street to Van Ness Avenue - Complete
- Peter Yorke Way from Geary Boulevard to Post Street - Complete
- McCormick Street from Pacific Avenue to End - Complete
Project Updates
- Monday, June 10th: grind existing asphalt from the roadway on Vallejo Street from Hyde Street to Jones Street, as well as on Jones Street from Vallejo Street to Broadway
- Tuesday, June 11th: re-pave Vallejo Street from Hyde Street to Jones Street
- Wednesday, June 12th: grind existing asphalt from the roadway on Pacific Avenue from Leavenworth Street to Polk Street
- Thursday, June 13th: re-pave Jones Street from Vallejo Street to Broadway as well as Pacific Avenue from Leavenworth Street to Hyde Street
- Friday, June 14th: re-pave Pacific Avenue from Hyde Street to Polk Street.
5/14/24: PLANNED CURB RAMP CONSTRUCTION ON WEBSTER STREET HAS BEEN POSTPONED. Instead, we will be starting curb ramp construction work on Larkin Street next Monday, May 20th.
First, we will begin constructing 2 new, ADA-compliant curb ramps at the intersection of Larkin Street and Rockland Street. Then, we will be constructing 6 new, ADA_compliant curb ramps at the NE, NW and SW corners of the Larkin Street and Vallejo Street Interseciton. Finally, we will be constructing 6 new, ADA-complaint curb ramps at the NE, NW and SW corners of the Larkin Street and Green Street intersection.
We expect this work to take three to four weeks to complete in total barring any unforeseen circumstances or inclement weather. There will be some restrictions to on-street parking on these blocks of Larkin Street while this work is taking place, but there are no planned street or lane closures. A few weeks after this work is complete, our crews will return to re-pave LarkinStreet from Union Street to Vallejo Street.
4/24/24: On Monday, April 29th through Wednesday, May 1st, we will be re-paving Scott Street between Chestnut Street and Lombard Street. The first step of this work is to repair a small patch of concrete street base in the center of the block that is currently damaged We will perform this work on Monday the 29th and Tuesday the 30th. Then, our crews will grind away the existing asphalt roadway surface and re-apply 2 new inches of asphalt to the roadway. We will be performing this work on Wednesday the 1st. This work should is expected to take three days to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
4/12/24: Starting April 16th, we will be replacing sewer laterals in two locations - on Pacific Avenue at the Polk Street intersection and on Leavenworth Street at the Clay Street intersection. We expect this work to take four days to complete in total at both locations. Once this work is complete, we will be constructing new, 10-inch thick concrete bus pads over the area that we've replaced sewer laterals. This bus pad construction work is scheduled to begin on April 25th. Once the concrete for these bus pads is poured, it will need a few days to properly dry and cure, and a portion of the street will need to be blocked off to all traffic to allow this to happen. Specifically, the bus pads will be constructed at the southeast corner of Leavenworth and Clay (in front of 1248 - 1258 Leavenworth) and at the northeast and southeast corners of Pacific and Polk (in front of 1572 Pacific and 1591 Pacific).
3/22/24: On Monday, March 25th, we will be re-paving Peter Yorke Way between Geary Boulevard and Post Street. The first step of this work is to grind away the existing asphalt roadway surface. Then, we will re-apply 2 new inches of asphalt to the roadway. This work should is expected to take one day to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
On Tuesday, March 26th and Wednesday, March 27th, we will be re-paving Bay Street between Franklin Street and Laguna Street. The first step of this work is to grind away the existing asphalt roadway surface. We will be performing this work on Tuesday the 26th. Then, we will re-apply 2 new inches of asphalt to the roadway. We will be performing this work on Wednesday the 27th. This work should is expected to take two days to complete barring any unforeseen circumstances or inclement weather. During construction, all on-street parking and through traffic will be prohibited until newly-laid asphalt reaches a safe temperature for vehicles to travel on. Local access to residents of the area will remain throughout the project.
From March 26th through the 28th, we will be constructing a new sewer manhole at the intersection of Pacific Avenue and McCormick Street. In order to perform this work, we will need to close McCormick Street to all vehicle traffic from 8am to 5pm on Tuesday, March 26th, Wednesday March 27th and Thursday, March 28th.This means that access to all garages and driveways on McCormick Street will be restricted during these times.
If you need to access your vehicle during these periods, please make other parking and vehicle access arrangements. Roadway, driveway and garage access will be restored each evening by 5pm.
We sincerely apologize for any inconvenience that this may cause, and assure you that we will be making these necessary sewer improvements in a quick and efficient way as possible.
A few weeks after we construct this new manhole, we will be coming back to build a new raised crosswalk across McCormick at the Pacific Avenue intersection. This may require similar temporary road closures. You will receive additional notice a few weeks prior to the start of this work.
Project Updates
San Francisco Public Works
Ronan Construction, Inc