Various Locations Pavement Renovation and Sewer Replacement No. 67B

Project Description

San Francisco Public Works has hired Michael O'Shaughnessy Construction, Inc. to complete infrastructure improvements on several blocks throughout the city as part of our Various Locations Pavement Renovations & Sewer Replacement Project #67B. This work will consist of roadway re-pavement, concrete base reconstruction, curb ramp construction, making them ADA compliant and sewer replacement work.

 

Project Update 

 

Traffic Signal Modifications Contract #36

Overview: February 2026 Update

 

The City continues to move forward with traffic signal upgrades and accessibility improvements at key intersections. Over the next three weeks, crews will be focused on completing signal punch list items, coordinating with utility providers, and finalizing curb ramp installations.

 

These efforts aim to enhance pedestrian safety, improve traffic flow, and support accessibility for all street users.

 

Work Schedule: January 19 – February 22, 2026

 

Folsom Streetscape/SOMA

Sign Up for Construction Updates Here

 

September 3, 2026

The Folsom Street project is in the final stages of construction, with crews focused primarily on completing punch-list items, remaining streetscape elements, and final installations. Work is progressing across all three segments, with several items scheduled to advance during the week of September 8.

 

Segment 3 -Folsom Street 2nd St. to 5th St

Better Market Street Shutdown

To allow construction crews to work in the roadway and in the Muni trackway, we will be shutting down Market Street between 5th and 8th Streets from 5:00am on Saturday, October 14th through Saturday, October 28th. During this period, we'll be temporarily moving above-ground transit off Market Street between 3rd Street and 10th Street to avoid the construction zone.

As-Needed Curb Ramp Construction for Street Resurfacing Program No.7

San Francisco Public Works has hired Precision Engineering, Inc. to construct new curb ramps at intersections throughout San Francisco. This project will include demolishing existing curb ramps & curbs, constructing new, ADA-compliant curb ramps and reconstructing adjacent areas of the sidewalk and curb lane.Work will be taking place at the following intersections:

Various Locations Pavement Renovation No. 56 and Sewer Replacement

San Francisco Public Works and the San Francisco Public Utilities Commission have partnered to complete infrastructure improvements on several blocks throughout San Francisco as part of our Various Locations #56 project. Our partnership allows us to minimize impacts to the public by consolidating our work whenever possible. This project will include sewer main replacement/rehabilitation, curb ramp installation, street base repairs, grinding (removal of existing asphalt) and repaving.

Various Locations Curb Ramps #10

San Francisco Public Works has hired R&S Construction Management, Inc. to construct new curb ramps at intersections throughout San Francisco. This project will include demolishing existing curb ramps & curbs, constructing new, ADA-compliant curb ramps and reconstructing adjacent areas of the sidewalk and curb lane. Work will be taking place at the following intersections: