Construction of the Inner Sunset Streetscape Improvement project began September 2017, after years of collaboration between city agencies and community partners. The two-year construction project, will improve the N Judah service, beautify nearby neighborhoods and make the streets more livable, vibrant and sustainable.
The project is a partnership between the San Francisco Municipal Transportation Agency (SFMTA), Public Works (SFPW) and the Public Utility Commission (SFPUC). The work under this contract consists of transit bulb-outs; curb ramps; sewer replacement; landscape improvements; electrical work; water line replacement and street paving along Irving Street between Arguello Boulevard and 19th Avenue, 9th Avenue between Irving and Judah streets, and 10th Avenue between Irving and Judah streets.
Additionally, streetscape improvements will occur at the existing transit bulb-outs in Cole Valley at Carl and Cole streets, as well as Carl and Stanyan streets.
The project is focused on improving the quality of life of the Inner Sunset and Cole Valley neighborhoods by upgrading existing infrastructure. Multiple improvements are incorporated into the project in order to avoid further disruptions and service shutdowns.
View more information at SFMTA - Muni Forward
Project Highlights:
- Sewer repair and replacement
- Water line replacement
- Auxiliary Water Supply System (AWSS) replacement
- Traffic Signal upgrades on Irving St. at the 5th and 8th Avenue intersections
- Department of Technology fiber optic installation
- MuniForward transit bulbouts and pedestrian bulbouts
- Road repaving and ADA curb ramp upgrades
Description of the scope of work:
- Sewer repair and replacement on Irving St. between Arguello Blvd. and 11th Ave., 15th and 18th Avenues, as well as 10th Ave. between Irving and Judah Streets
- Water line replacement on Irving St. between Arguello Blvd. and 12th Ave., 17th and 19th avenues, as well as 11th Ave. from Irving to Judah streets and 12th Ave. from Lincoln Way to Judah St.
- Auxiliary Water Supply System (AWSS) replacement on Irving St. between 7th and19th Avenues
- Traffic Signal upgrades on Irving St. at the 5th and 8th Avenue intersections
- Department of Technology fiber optic installation on Irving St. between 9th and19th Avenues
- Muni Forward transit bulbouts on Irving Street at 5th, 6th and 8th Avenues, as well as 9th Ave. between Irving and Judah streets. Pedestrian bulbouts at the northwest corner of 7th Ave. and Irving St., and the southeast corner of 9th Ave. and Irving St.
Road repaving and curb ramp upgrades on Irving Street between Arguello Blvd. and 19th Ave., and 9th and 10th Avenues between Irving and Judah Streets
Due to construction, neighborhoods will experience short-term inconveniences:
- Bus substitution for the N-Judah Line will occur at the end of the project during final roadway paving.
- Temporary relocation of bus stops, street parking removal, and temporary traffic lane and sidewalk closures
- Noise during excavation
- Reduced traffic lanes and traffic back-ups
Project Renderings:
Mitchell Engineering
San Francisco Public Works