3734 Folsom Street

Site: 1

Reason(s) for Tree Removal: Necessary sidewalk repair will require roots be pruned. Amount of root pruning expected to destabilize and likely kill tree. Site unsustainable for mature size of species. Major stem does not meet rquired clearance over road. Location is not replantable.

Posting Period: 03/16/26 - 04/15 26

532 Peralta Ave

Site: 1

Reason(s) for Tree Removal: Sidewalk is impassable due to root uplift of 2" across entire width of path. Current width of right of way is less than ADA requirement of 3'. Location  is not replantable.

Posting Period: 03/16/26 - 04/15/26

538 Peralta Ave.

Site: 1

Reason(s) for Tree Removal: Excessive sidewalk uplift to be corrected through sidewalk repair. Current path of travel does not meet ADA width requirements. Trunk does not allow for minimum sidewalk width of 3' following sidewalk repair. Location is not replantable.

Posting Period: 03/16/26 - 04/15/26

121 Richland Ave.

Site: 3

Reason(s) for Tree Removal: Cracking and decay at base of multiple main stems following past failure. Future, similar failures expected. Risk cannot be ameliorated through pruning. Location is replantable. 

Posting Period: 02/23/26 - 03/25/26

801 Silver Ave.

Site: 15

Reason(s) for Tree Removal: Extensive internal decay with seam to the base of the tree. Significant roots pruned for necessary sidealk repair. Location is replantable.

Posting Period: 02/23/26 - 03/25/26

13th Street Safety Improvement Project

Sign up to receive construction updates via email here
 
Project Update (Last updated in March 2026)
The contractor has completed the fence realignment work in front of the Division Circle Navigation Center. 
 
Crews continue curb ramp work at the 13th Street and Folsom Street intersection. This work is expected to continue for a few more weeks.  

Various Locations Curb Ramps #17

Project Description

San Francisco Public Works has hired Sage Consulting Engineers, Inc. to construct new curb ramps at intersections throughout San Francisco. This project will include demolishing existing curb ramps & curbs, constructing new ADA-compliant curb ramps and reconstructing adjacent areas of the sidewalk and curb lane. The scope of work will include saw-cutting the sidewalk and gutter, removing concrete, framing and pouring concrete and placing asphalt in the gutter area.

Traffic Signal Modifications Contract #36

Overview: February 2026 Update

 

The City continues to move forward with traffic signal upgrades and accessibility improvements at key intersections. Over the next three weeks, crews will be focused on completing signal punch list items, coordinating with utility providers, and finalizing curb ramp installations.

 

These efforts aim to enhance pedestrian safety, improve traffic flow, and support accessibility for all street users.

 

Work Schedule: January 19 – February 22, 2026