2700 Bryant St

Site: 1

Reason(s) for Tree Removal: Roots are uplifting sidewalk and impeding access to adjacent fire exit to buliding. Significant sidewalk uplift is along primary path to adjacent school from bus stop. Required root pruning will severely impact health of tree. Significant decay in trunk cavity from previous branch failure has an increased risk of trunk failure given species failure profile. Location is replantable. 

Posting Period: 06/29/26 - 07/14/26

2450 Harrison St

Site: 2

Reason(s) for Tree Removal: Recent failure has destabilized remaining branches. Tree will be pruned to address immediate hazard, but will be too severe to retain tree. Location is replantable. 

Posting Period: 06/29/26 - 07/29/26

2450 Harrison St

Site: 1

Reason(s) for Tree Removal: Roots are uplifting sidewalk and impeding access to adjacent fire exit to buliding. Significant sidewalk uplift is along primary path to adjacent school from bus stop. Required root pruning will severely impact health of tree. Significant decay in trunk cavity from previous branch failure has an increased risk of trunk failure given species failure profile. Location is replantable. 

Posting Period: 06/29/26 - 07/29/26

200 Bartlett St

Site: 8

Reason(s) for Tree Removal: Necessary electrical upgrades require citing of new electrical service yard main switchboard and transformer in schoolyard. This new construction necessitates the shifting of the existing driveway into the location of tree to be removed. Location is replantable. Permit  806935

SITE PLAN

Posting Period: 06/01/26 - 07/01/26

Various Locations Curb Ramps #17

Project Description

San Francisco Public Works has hired Sage Consulting Engineers, Inc. to construct new curb ramps at intersections throughout San Francisco. This project will include demolishing existing curb ramps & curbs, constructing new ADA-compliant curb ramps and reconstructing adjacent areas of the sidewalk and curb lane. The scope of work will include saw-cutting the sidewalk and gutter, removing concrete, framing and pouring concrete and placing asphalt in the gutter area.

Traffic Signal Modifications Contract #36

Overview: February 2026 Update

 

The City continues to move forward with traffic signal upgrades and accessibility improvements at key intersections. Over the next three weeks, crews will be focused on completing signal punch list items, coordinating with utility providers, and finalizing curb ramp installations.

 

These efforts aim to enhance pedestrian safety, improve traffic flow, and support accessibility for all street users.

 

Work Schedule: January 19 – February 22, 2026

 

Various Locations Pavement Renovation and Sewer Replacement Project No. 53

Construction Updates


7/19/24: As of today, we have reached substantial completion on this project. This means that all planned paving, sewer, curb ramp and sidewalk has been completed, and we are now entering the closeout phase of the project. During the closeout phase, all work is re-inspected and minor fixes are performed by our contractor wherever necessary.