Mission Street & Mount Vernon Avenue Sewer Project

Replacement of the sewer main continues along Mission Street. In order to expedite the work, the contractor has chosen to use two crews along Mission Street. The first crew continues working Southward on Mission Street between Foote Avenue and Naglee Street. The second team is currently working at the Mission and Farragut intersection and will continue Southward until reaching the Oliver Street intersection.

Lawton Avenue Pavement Renovation

Project Information 

The Department of Public Works is making pavement renovations along Lawton Avenue from the Lower Great Highway to 28th Avenue ( 18-blocks). This work includes the addition of new curb ramps, concrete base repairs, asphalt grinding and finally paving.