Various Locations Pavement Renovation and Sewer Replacement No. 8
Project Update (February 02/10/2022)
Project Update (February 02/10/2022)
San Francisco Public Works and the San Francisco Public Utilities Commission have partnered to complete infrastructure improvements on several neighborhood blocks. Our partnership allows us to minimize impacts to the public by consolidating work whenever possible.
The contractor has completed sewer main replacement work on Ortega Avenue. The final paving work has been completed between 24th Avenue and 29th Avenue. Final paving between 19th Avenue and 24th Avenue will be scheduled in the coming weeks. Ortega Street is the last location under this contract.
San Francisco Public Works has contracted with Precision Engineering, Inc. to install new sewer utilities and renovate the roadway at various locations in District 7 as part of the Various Locations Sewer Replacement and Pavement Renovation No.
For email updates, please sign up here.
The Parkmerced/Twin Peak/Mt. Davidson Manor residential Street Resurfacing Project will consist of traffic routing, pavement renovation, ADA curb ramp installation, sewer replacement and all associated work at various locations throughout San Francisco.
Work Locations:
Project Background
Construction of the Inner Sunset Streetscape Improvement project began September 2017, after years of collaboration between city agencies and community partners. The two-year construction project, will improve the N Judah service, beautify nearby neighborhoods and make the streets more livable, vibrant and sustainable.
The project is a partnership between the San Francisco Municipal Transportation Agency (SFMTA), Public Works (SFPW) and the Public Utility Commission (SFPUC). The work under this contract consists of transit bulb-outs; curb ramps; sewer replacement; landscape improvements; electrical work; water line replacement and street paving along Irving Street between Arguello Boulevard and 19th Avenue, 9th Avenue between Irving and Judah streets, and 10th Avenue between Irving and Judah streets.
Additionally, streetscape improvements will occur at the existing transit bulb-outs in Cole Valley at Carl and Cole streets, as well as Carl and Stanyan streets.
The project is focused on improving the quality of life of the Inner Sunset and Cole Valley neighborhoods by upgrading existing infrastructure. Multiple improvements are incorporated into the project in order to avoid further disruptions and service shutdowns.
View more information at SFMTA - Muni Forward
Project Highlights:
Description of the scope of work:
Road repaving and curb ramp upgrades on Irving Street between Arguello Blvd. and 19th Ave., and 9th and 10th Avenues between Irving and Judah Streets
Work Locations and Approximate Timeline:
Project Description
San Francisco Public Works has partnered with the San Francisco Public Utilities Commission to complete much needed infrastructure upgrades along Lawton Street. Public Works is managing the project and has hired Esquivel Grading and Paving, Inc. to complete the work. The project will include sewer main replacement, spot sewer repairs, catch-basin and culvert work, curb ramp construction, concrete street base repairs and repaving. Not all blocks will include sewer main replacement work.