Harrison Street Improvement Project
Project Description:
Project Description:
Project Update (February 02/10/2022)
Project Update (August 2025)
This project has been completed.
San Francisco Public Works and the San Francisco Public Utilities Commission have partnered to complete infrastructure improvements on several neighborhood blocks. Our partnership allows us to minimize impacts to the public by consolidating work whenever possible.
Project Update (Week of 12/14/2020)
SFWD is scheduled to begin pressure testing the new line AWSS line at the Haight/Fillmore intersection. Due to the scope of work, the line will be tested in the evening. The work is scheduled for the evening of Wednesday December 16, 2020 at 8 PM and is expected to conclude by 10 PM. On Thursday, crews will back-fill the trench and begin apply temporary pavement to the area. In January 2021, our contractor will return to schedule permanent paving at the intersection.
Project Status
The Minna–Natoma Streetscape Project continues to move forward, with several important milestones completed as the project prepares for its next major phase.
The construction team has successfully completed sewer improvement work along Natoma Street, marking a significant achievement for the project. In addition, all project redesigns have been completed and approved, and the artwork planned for the streetscape has also received final approval.