Public Works Hearing
Notice is hereby given that the Director of Public Works will hold a remote public hearing via teleconference to consider the item(s) listed below and that said public hearing will be held as follows:
DATE: September 16th, 2026
Time: 10:00am
Public Works Hearing
Notice is hereby given that the Director of Public Works will hold a remote public hearing via teleconference to consider the item(s) listed below and that said public hearing will be held as follows:
DATE: September 30th, 2026
Time: 10:00am
Public Works Hearing
Notice is hereby given that the Director of Public Works will hold a remote public hearing via teleconference to consider the item(s) listed below and that said public hearing will be held as follows:
DATE: September 23rd, 2026
Time: 10:00am
VL Contract 35 Traffic Signals
Schedule revised November 3, 2026 | October 26–November 23, 2026
Upcoming Construction Activities
Construction crews will continue work at several intersections throughout the project area over the coming weeks. Activities will include installing foundations for new streetlights, electrical conduits and pull boxes, and temporary sidewalk and pavement restoration.
Here’s what to expect at the following locations:
Various Locations Pavement Renovation No. 82 and Sewer Replacement
Project Description
San Francisco Public Works has contracted Ronan Construction, Inc. to deliver the Various Locations Pavement Renovation No. 82 and Sewer Replacement project.
This multi-location infrastructure project will improve roadway conditions, pedestrian accessibility, drainage and sewer infrastructure at several locations throughout San Francisco. Construction is anticipated to begin in November 2026 and continue for approximately 470 calendar days.
Project Locations
Public Works Hearing
Notice is hereby given that the Director of Public Works will hold a remote public hearing via teleconference to consider the item(s) listed below and that said public hearing will be held as follows:
DATE: September 2nd, 2026
Time: 10:00am
Various Locations Pavement Renovation #90 & Sewer Replacement Project
Project Update
Our contractor will begin working on 14th Ave. and 15th Ave. on Monday October 05, 2026. Work on this portion of 14th and 15th avenues will be completed by the end of October barring any rain delays or unforeseens.
Various Locations #77 Paving and Sewer Renovations
November 2026
Upcoming construction: October 26 – November 14, 2026
Construction crews with Esquivel Grading & Paving will continue work at several locations throughout San Francisco as part of the VL77 Pavement Renovation No. 77 and Sewer Replacement Project. Over the coming weeks, crews are scheduled to perform sewer repairs and replacements, roadway base repairs, pavement grinding and paving, and work on bus pads and speed cushions.