136 Randolph St

Site: 1

Reason(s) for Tree Removal: Tree leans into public right of way at a severe angle, blocking sidewalk access. Pruning will not alleviate blockage. Large wound along trunk has decay exacerbated by horizontal exposure to rain. Location is replantable. 

Posting Period: 08/24/26 - 09/23/26

Union Street Pavement Renovation and Sewer Replacement Project

Project Update
Once construction is scheduled to break ground, we'll send out regular e-updates. Please sign-up HERE to receive updates. Thank you. 
 

Project Description
The Union Street Pavement Renovation and Sewer Project seeks to address aging infrastructure along one of San Francisco’s historic dining and shopping districts. The project limits are Union Street between Lyon Street and Powell St (29 blocks).

Various Locations Pavement Renovation No. 85 and Sewer Replacement

San Francisco Public Works has contracted with Esquivel Grading and Paving, Inc. to improve sewer utilities and renovate the roadway at various locations in San Francisco as part of the Various Locations Pavement Renovation and Sewer Replacement Project No. 85 (VL85). We will be performing this work in the Western Addition, Marina, Cow Hollow Laurel Heights, Outer Richmond, Haight Ashbury and Pacific Heights neighborhoods. 

 

Various Locations (VL) #62

Sign up for Project Updates Here: 
 

September Update 2026

 

Happening This Week 9/7/2026 

Mason Street (O'Farrell Street to Ellis Street)

  • Roadway grinding on Tuesday, 9/8/26 and final roadway paving on Thursday, 9/9/26.

 

Cyril Magnin (Ellis street to Market Street)

8th St, Clay St, and Leavenworth St. Pavement Renovation and Sewer Replacement Contract #2308i

For Electronic Newsletter Updates Sign up Here
 

Construction Update August 3, 2026

 

Scheduled construction activities will continue through mid-August. 

Crews will be completing sewer lateral work at 200 8th Street and mortar repair work along 8th Street

Various Locations Pavement Renovation and Sewer Replacement No. 67B

Project Description

San Francisco Public Works has hired Michael O'Shaughnessy Construction, Inc. to complete infrastructure improvements on several blocks throughout the city as part of our Various Locations Pavement Renovations & Sewer Replacement Project #67B. This work will consist of roadway re-pavement, concrete base reconstruction, curb ramp construction, making them ADA compliant and sewer replacement work.

 

Project Update 

 

Various Locations Curb Ramps #17

Project Description

San Francisco Public Works has hired Sage Consulting Engineers, Inc. to construct new curb ramps at intersections throughout San Francisco. This project will include demolishing existing curb ramps & curbs, constructing new ADA-compliant curb ramps and reconstructing adjacent areas of the sidewalk and curb lane. The scope of work will include saw-cutting the sidewalk and gutter, removing concrete, framing and pouring concrete and placing asphalt in the gutter area.

Traffic Signal Modifications Contract #36

Overview: February 2026 Update

 

The City continues to move forward with traffic signal upgrades and accessibility improvements at key intersections. Over the next three weeks, crews will be focused on completing signal punch list items, coordinating with utility providers, and finalizing curb ramp installations.

 

These efforts aim to enhance pedestrian safety, improve traffic flow, and support accessibility for all street users.

 

Work Schedule: January 19 – February 22, 2026