Various Locations Pavement Renovation and Sewer Replacement No. 8
Project Update (February 02/10/2022)
Project Update (February 02/10/2022)
Project Update (August 2025)
This project is complete except for minor punch list work that continues.
San Francisco Public Works and the San Francisco Public Utilities Commission have partnered to complete infrastructure improvements on several neighborhood blocks. Our partnership allows us to minimize impacts to the public by consolidating work whenever possible.
Project Update (Week of 12/14/2020)
SFWD is scheduled to begin pressure testing the new line AWSS line at the Haight/Fillmore intersection. Due to the scope of work, the line will be tested in the evening. The work is scheduled for the evening of Wednesday December 16, 2020 at 8 PM and is expected to conclude by 10 PM. On Thursday, crews will back-fill the trench and begin apply temporary pavement to the area. In January 2021, our contractor will return to schedule permanent paving at the intersection.
Project Update (April 2026)
Project Status
The Minna–Natoma Streetscape Project has completed a comprehensive redesign and is scheduled to resume active construction on April 3, 2026.
Construction activities will restart on Natoma Street at New Montgomery Street, beginning with sewer system improvements.
The contractor has completed sewer main replacement work on Ortega Avenue. The final paving work has been completed between 24th Avenue and 29th Avenue. Final paving between 19th Avenue and 24th Avenue will be scheduled in the coming weeks. Ortega Street is the last location under this contract.