Safer Taylor Street
Project Update (August 2025)
This project has been completed.
Project Update (August 2025)
This project has been completed.
San Francisco Public Works and the San Francisco Public Utilities Commission have partnered to complete infrastructure improvements on several neighborhood blocks. Our partnership allows us to minimize impacts to the public by consolidating work whenever possible.
Project Update (Week of 12/14/2020)
SFWD is scheduled to begin pressure testing the new line AWSS line at the Haight/Fillmore intersection. Due to the scope of work, the line will be tested in the evening. The work is scheduled for the evening of Wednesday December 16, 2020 at 8 PM and is expected to conclude by 10 PM. On Thursday, crews will back-fill the trench and begin apply temporary pavement to the area. In January 2021, our contractor will return to schedule permanent paving at the intersection.
Project Status
The Minna–Natoma Streetscape Project continues to make steady progress as construction advances through the South Downtown neighborhood.
The construction team has successfully completed the sewer improvement work along Natoma Street, marking a significant milestone for the project. With this phase complete, crews have transitioned into the next stage of construction and are now performing roadway and utility improvements along Natoma Street and New Montgomery Street.
The contractor has completed sewer main replacement work on Ortega Avenue. The final paving work has been completed between 24th Avenue and 29th Avenue. Final paving between 19th Avenue and 24th Avenue will be scheduled in the coming weeks. Ortega Street is the last location under this contract.
Project Description
The Market and Octavia Living Alleys project aims to create a public realm that strengthens the community, creates a sense of identity and makes a more useful, safe and attractive neighborhood.